Tracking Costs and Budgets

 

Introduction

 

Geniusproject has been designed to support multi-currency and multi-rate management. This chapter presents cost and budget management features. It should be treated as a guideline and not a rule since each organization typically has its own rules with regards to cost management.

The first financial component that is addressed in Geniusproject is "Rates Management". A "rate" in the application can refer to one of two things; a resource’s internal cost or their external/ billable cost.

Geniusproject supports several levels of resource rates management and multi-rates management for each company and resource in the [Resources] module. Geniusproject provides the flexibility to assign standard rates to companies and resources while allowing for specific rate changes at the project or task level. A standard/ default rates document is defined during the setup of the "Resources" module. It includes default rates as well as rates by activity type if "Multi-rate management" has been enabled in the General setup document.

The second financial component addressed in Geniusproject is the project budget. Project budgets can either be global, one for an entire project, or broken out across periods. They are used to forecast or capture planned labor (internal and external) and non-labor costs and can be built using one or two axes, for example by activity type and/or cost center.

The third financial component Geniusproject addresses is multi-currency management. It is possible to define one main currency and up to ten secondary currencies, and company and resource rates can be defined using any one of them. If multiple [Projects] modules exist, each module can have any one of the currencies defined in the [Portfolio] module as its main currency, and a secondary currency can be used primarily for display purposes. The same goes for "Archive" or "Consolidation" databases. It is also possible to define monthly exchange rates in order to be more accurate.

 

Rate Management

 

Geniusproject supports multi-rate and multi-level rate management for the different companies and individuals listed in the Resources module. Geniusproject offers the flexibility to assign default rates to companies and resources while allowing specific rate changes at the project or task level. In this document, "Rate" includes two elements, the internal cost of the resource, and the resource’s billable cost.

The "Standard rates" document lets you capture default rates and rates by activity type, provided that "Multi-rate management" has been enabled in the "General" setup document.

 

Multi-Rate Management

 

Multi-rate management is an optional feature, which can be enabled in the "General" setup document of the [Resources] module.

Multi-rate management allows companies to assign different rates to their resources depending on the type of work or activity they are performing in a project.

Geniusproject supports up to 11 different rates for companies and resources.

Each resource will have a "default" rate and then up to ten other potential rates that will vary depending on the activity type of the tasks they are working on. When calculating a resource’s cost for work on a particular task, the system will automatically use the rate associated to the activity type defined in the task. If the activity type has not been defined, or if there is no specific rate assigned to the activity, the system will automatically use the default rate.

Note: The activity types are defined in the "General" setup document of the Resources module, as well as the "Keywords lists" setup document of each of the Projects modules.

 

Assigning Rates

 

In the Resources module, The "Standard rates" setup document lets you define default rates, as well as standard rates by activity type, when "Multi-rates management" has been enabled in the "General" setup document.

When creating a resource, their rates are populated with the standard rates for the company and location they belong to. It is however, possible to change the resource’s rates by deselecting "Import the rates" on the Rates tab of their profile document.

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img82

It is possible to change the rates allocated to a resource for all projects in a Projects module. Rates can be changed directly in the "Resource" record of a Projects module, after the "Resource" and "Company" documents have been published to it. To do so the "Import the rates"" option must be disabled.

It is possible to change the rates allocated to a resource at the individual project level. By selecting "Rate" from the Create menu in the Project Description form, a new "Rates" definition record can be defined, unique to the active project.

Note: The "Project Description" form must be in edit mode.

 
Note: In previous version, some actions did automatically create project rates (project created from template, resource renamed), without want or need. Now the project rates are only created with the actions "Import the rates" and "Update the resources rates".
 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img83

You can also change a resource’s rates at the task level by clicking on the GP V7.2 User Manual_20131115 - CI_GI - 07-10_img84 icon on the Resources tab of the Task form. See "Rate updates" below.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img85

 

How Genius Project Manages Rates

 

We have included the chart below to demonstrate further Geniusproject’s of allocating a rate to a task.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img86

 

 

Tracking Task Cost

 

Geniusproject offers two possible ways to post time so workload costs can be tracked:

  • Using the Timesheets module: Users enter their workload details in a timesheet. They user can also propose a new "remaining" time, that must be accepted or rejected by the project manager.
  • Without using the Timesheets module: Users can enter their workload details directly in the assignment form. The user can also specify the "remaining". Once the assignment is saved, the task will automatically be updated with the new information and the effective and remaining costs will be calculated automatically in the task, using the resource’s rate.

 

Updating Rates

 

If a company’s list of standard (default) rates has been modified, you can update them in all the companies by using the Actions \ Update resources rates action located in the Standard rates setup view.

When creating a new resource, they will inherit the standard rates from the company and location they belong to.

If the company’s rates have been modified, the changes can be applied to all company resources by navigating to the General tab of the Resources module setup and selecting Update the resources rates from the Actions menu.

Note: The updates will only be applied as long as the option to Import the rates has been enabled in the "Resource" forms. 

Resources can be published to or updated in the different Projects module(s), by navigating to the Resources tab -> Resource list view in the contextual navigation menu and selecting either of the Publish option from the Destinations dropdown menu. . The resources" rates are updated at the same time if the "Import the rates" option is enabled in the "Resource" documents in the Projects module(s), or if the resource was not previously published in the Projects module(s).

 

Cost Centers

 

As an alternative to basing rates on resource type, Geniusproject also offers the option of using cost centers. Each resource can be linked to one cost center.

Cost centers are defined in the General setup document of the Resources module. They can then be selected in the Rates section of each Resource document.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img87

Once the cost centers are defined in the "Resource" documents, and the resources are published in all destination modules (see Resources administration), then the cost centers are automatically available in the Timesheets module.

  • Timesheets
  • Timesheet details
  • Expense report
  • Expense details

In the Projects module, the cost center is automatically available and used for calculation in the following documents:

  • Timesheet details
  • Assignments

It is also possible to select the cost center in the Cost documents of the Projects module, with the exception of "Cost" documents created from the "Expense sheet" where the field "Cost center" is computed from the "Expense detail" document.

The cost centers could also be used in detailed Budgets to categorize budget lines.

There are no standard views showing information categorized by cost center, but they can easily be developed and added. See Customize  Geniusproject for further information.

 

Multi-Currency Management

 

Geniusproject lets you manage a main currency and up to 9 secondary currencies.

The main and secondary currencies are defined in the Currencies tab of the "General" setup of each Projects module.

Therefore it is possible:

  • To capture costs documents in any currency entered into the system.
  • To see task costs in both the main currency and the first secondary currency.
  • To create views using either the main currency or the first and/or secondary currency.

 

Updating the Exchange Rate

 

Geniusproject lets you define exchange rates by month for the secondary currencies. If there is no exchange rate for the current month, the default rate defined in the "General" setup form is used.

To create monthly exchange rates, access the Projects modules "Setup" context, select the Exchange rate view and use the New periodic rates action.

 

The Budget

 

A project budget is always created with the creation of a new project. Depending on the setup there can be one or several budgets for a project. Projects with multiple budgets have been broken out into periods. To find out more about budgets by period, see the chapter on advanced budget management. The chapter deals solely with the default configuration, one budget per project.

There are two ways to access a project’s budget:

  • Click on the "Budget" link in the "Cost & Budget" of the Project Description document.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img88

 

  • Or, navigate to the Projects tab.
  • Select Costs & Budget from the contextual navigation menu.
  • Select Budget and then the budget you would like to open from the choices in the content window.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img89

The budget form allows you to define all aspects of the project’s budget. Geniusproject defines the budget using the following axes (categories):

  • Internal work (labor): All of the hours worked by "internal" resources.
  • External work (labor): All of the hours worked by "external" resources (subcontractors, partners, etc.).
  • Investment & Expenses (non-labor): All non-labor related costs (purchases, travel costs, rentals, etc.).

There are two types of budget formats, a detailed budget and a flat non-detailed one. They both originate from the same form but depending on the selected format, the available options will be different.

 

The Budget Header

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img90

Project

The project that the budget belongs to.

This is the main identifier of the project. It can be the project name or name and code, depending on what has been defined in the General setup document of the [Projects] module. The project name and code are entered in the Project description document and are included in all of the project documents.

The label is a link to open the corresponding "Project description" document directly.

Project leader

The project’s main project leader (as opposed to the project leader substitute)

Deadline

Version number

Version

Document version number

Last modification

Date and time of the last modifications. By clicking on the date you can access the history of the modifications

Last Comment

Displays the last comments made on the budget. You can reply directly to the comments by clicking on "Reply" and you can create a new discussion by clicking on "New discussion". See "Collaborate with Genius Live!" for more information.

 

Non-Detailed Budgets Definition

 

For a non-detailed budget, a pool of days for labor will be defined, split across internal and external resources. There will be a defined total for internal cost as well as external cost if the project billable.

A global amount will also be defined for investments and expenses, all non-labor costs.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img91

Billing mode

Possible billing mode options are:

Fixed price

Not billable

Time and material

Not editable, the value is inherited from the project description.

Detailed budget

Select No for not detailed budget.

Internal labor

Days

Amount of labor budgeted for internal resources.

Budget

Budgeted cost for labor by internal resources.

Billing

Amount of billable labor budgeted for internal resources.

Not displayed if project is not billable.

Margin

Budgeted margin on internal labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

External labor

Days

Amount of labor budgeted for external resources.

Budget

Budgeted cost for labor by external resources.

Billing

Budgeted billing amount for labor by external resources.

Not displayed if project is not billable.

Margin

Budgeted margin on external labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

Investments & Expenses

Budget

Budgeted amount for non-labor costs

Billing

Budgeted billing amount for non-labor costs.

Not displayed if project is not billable.

Margin

Budgeted margin on non-labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

Total

Days

Total budgeted labor days (workload)

Budget

Total budgeted cost for the project

Billing

Total budgeted billable amount. Not displayed if project is not billable.

Margin

Budgeted total margin on internal labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

 

Detailed Budget

 

As its name suggests, this budget format allows you to include more layers of detail in your budget. Instead of just defining high level of labor and non-labor related costs, the detailed budget allows costs to be defined at a more granular level; by activity type.

The axis or axes used to make up the budget are defined in the General setting of the Portfolio module. For the purposes of this chapter we will be focusing on the default single axes selection, which can be defined as activity and cost types. For more information see the chapter on advanced budget management.

The first is somewhat the same as that of the non-detailed budget, however now it displays consolidated totals of the information detailed out on the Internal Labor, External Labor and Inv. & Exp tabs.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img92

 

The Description Tab

 

Billing mode

Possible billing mode options are:

Fix price

Not billable

Time and material

Not editable. Inherited from the project description document.

Detailed budget

Select "Yes" for detailed budget.

Internal labor

Days

Amount of labor budgeted for internal resources.

Computed. Total number days defined on the [Internal labor] tab.

Budget

Budgeted cost for labor by internal resources.

Computed. Total of cost defined in the Internal labor tab.

Billing

Budgeted billable amount for labor by internal resources.

Computed. Total amount defined on the Internal labor tab.

Not displayed if project is not billable.

Margin

Budgeted margin on internal labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

External labor

Days

Amount of labor days budgeted for external resources.

Computed. Total number of days defined on the External labor tab.

Budget

Budgeted cost for labor by external resources.

Computed. Total cost defined in the External labor tab.

Billing

Billable amount budgeted for labor by external resources.

Computed. Total amount defined in the External labor tab.

Not displayed if project is not billable.

Margin

Budgeted margin on external labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

Investments & Expenses

Budget

Budgeted amount for non-labor costs.

Computed. Total of costs defined in the Inv & Exp tab.

Billing

Budgeted billable amount for non-labor costs.

Computed. Total amount defined in the Inv & Exp tab

Not displayed if project is not billable.

Margin

Budgeted margin on non-labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

Total

Days

Total amount of days budgeted for labor (workload).

Budget

Total cost budgeted for the project.

Billing

Total budgeted billing amount.

Not displayed if project is not billable.

Margin

Budgeted total margin on internal labor cost.

Computed = Budgeted – billing.

Not displayed if project is not billable.

 

The Internal Labor Tab

 

This tab is used to define the detailed breakdown of workload and costs for internal labor. The user can add as many lines as necessary to the grid; one activity type per line. The list of available activity types is created as part of the keyword configuration in the setup of the module.

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img93

Grid
buttons

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img6

To add a new line to the budget.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img7

To remove a selected line from the budget.

Grid

Activity type

The activity type the budget line is being defined for.

Days

Amount of days budgeted for labor by internal resources.

Budget

Budgeted cost of labor by internal resources.

Billable

Budgeted billable amount for labor by internal resources.

Not displayed if project is not billable.

Margin

Budgeted margin on internal labor cost.

Not displayed if project is not billable.

 

 

The External Labor Tab

 

Same as the Internal labor tab however values are defined for external labor. 

 

The Inv. & Exp. Tab

 

This tab is used to define the details non-labor related costs, referred to in Geniusproject as "Investments and expenses". The user will be able to create as many entries as necessary in the data entry form. Normally input by cost type. The cost types of are defined in the configuration of keywords.

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img96

Grid
buttons

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img6

To add a new line to the budget.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img7

To remove a selected line from the budget.

Grid

Cost type

The type of cost the budget line is being defined for.

Budget

Budgeted cost.

Billable

Budgeted billable amount.

Not displayed if project is not billable.

Margin

Budgeted margin.

Not displayed if project is not billable.

 

  

Non Labor Costs, Investments & Expenses

 

All non-labor related costs (purchases, travel expenses, rentals, etc.) can be tracked using "Costs" documents.

By entering the costs and their planned values in advance, it is possible to have a more complete overview of the anticipated and fixed budget.

 

Creating a cost

 

To create a new cost:

  • From the Projects tab navigate to the Costs & budgets view in the contextual navigation menu.
  • Click New cost.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img99

 

Note: A new Cost can also be created using the Create button on the action menu bar and selecting Cost.

 

Cost Header

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img100

Cost

The Cost title. Mandatory. Describes the cost, for example a server, a plane ticket, etc.

Project

The project that the Cost belongs to.

The label is a link that opens the corresponding "Project description" document directly.

Phase

The project phase the Cost is associated with.

Project leader

The project’s main project leader (as opposed to the project leader substitute)

Deadline

Visual indicators if there is an associated workflow:

Red, deadline passed

Orange, deadline will not be met according to remaining workload

Green, OK.

Version

Version number.

Modified on

Date and time of the last modifications. By clicking on the date you can access the history of the modifications.

Last Comment

Displays the last comments made about the cost. You can reply directly to the comment by clicking "Reply" and you can create a new discussion by clicking on "New discussion". See "Collaborate with Genius Live!" for more information.

 

Defining the Cost Details

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img101

General

Type

The type of cost. Single selection field. The list of choices comes from the cost types defined in the Keywords & Labels setup document. Not editable if the cost was created from the Timesheets module. Mandatory.

Order No

The purchase order number. Free text. Mandatory only if the "Cost" document is indeed a Purchase order.

Requester

By default, the name of the author of the "Cost" document. Single selection field. Can be selected from the participants of the project. Not editable if the cost was created from an expense sheet. Mandatory.

Cost center

The cost center the cost is linked to. By default, the cost center the author belongs to. Single selection field. The list of choices comes from the cost centers defined in the General setup document of the Resources module. Not editable if the cost was created from the Timesheets module.

Plan

Only active if the document is a deliverable converted into a cost. If the deliverable was created from a plan, the title of the plan is shown, and the field is a shortcut that opens the corresponding Plan document.

Otherwise, it displays the label "Upload into", and the value for the field is "- Select a plan -", which is a shortcut allowing for the selection of the "Plan" document the cost should be uploaded into (as a deliverable). The cost will be uploaded the next time the plan is saved. In the meantime, the label Upload into becomes a shortcut which can be used to cancel the upload.

Capital

Yes or No. To indicate if the cost is to be considered as capital or not. This field has no impact in the application.

Billing mode

The billing mode that applies to the cost. Single selection field. Possible values are:

Not billable: nothing is billed.

Fixed price: the billing price is fixed in advance. It will be recorded through the "Billable amount" field

Actual amount: the billable amount will be equal to the actual amount of the cost.

Not editable if the cost was created from the [Timesheets] module.

Billing state

Not visible if Billing mode is set to Not billable. To indicate if the cost is already billed or not. Single selection field. Possible values are:

Billed

Not billed

Partly billed

Details

Other currency

Clicking on this link displays all amounts in each currency defined in the field "Other currencies" of the General setup document.

Planned amount

The amount planned for the cost. Not editable if the cost was created from an expense sheet

Currency

The currency of the cost. Single selection field. The list of choices comes from the field "Other currencies" defined in the "General" setup document. By default the project currency.

Not editable if the cost was created from the Timesheets module.

If the choice is different from the Projects modules reference currency, the system automatically calculates and displays the planned amount in the reference currency. Not editable if the cost was created from the Timesheets module.

 

The GP V7.2 User Manual_20131115 - CI_GI - 07-10_img102 icon automatically fills the actual amount and the actual date with the planned amount and the date.

Planned date

The date the amount is planned to be paid.

Actual amount

The actual amount of the cost.

Actual date

The date the actual amount is confirmed.

Billable Amount

The forecasted amount to bill.

Not visible if Billing mode is set to Not billable. The planned billable amount.

 

Not editable if "Billing mode" is set to "Actual amount" or if the cost was created from an expense sheet.

Billable date

The date the amount is expected to be billed on.

 

Not visible if "Billing mode" is set to "Not billable". The planned billable amount.

Billed amount

Final billable amount.

Not visible if "Billing mode" is set to "Not billable" or if "Billing state" is "Not billed". The actual billed amount.

Not editable if "Billing mode" is set to "Actual amount" or if the cost was created from an expense sheet.

Currency

Not visible if "Billing mode" is set to "Not billable" or if "Billing state" is "Not billed". The currency in which the amount was billed. Single selection field. The list of choices comes from the field "Other currencies" defined in the "General" setup document.

Not editable if "Billing mode" is set to "Actual amount" or if the cost was created from an expense sheet.

If the choice is different from the Projects module reference currency, the system automatically calculates and displays the actual billed amount in the reference currency.

Not editable if "Billing mode" is set to "Actual amount" or if the cost was created from an expense sheet.

Billing date

Effective billing date.

Not visible if "Billing mode" is set to "Not billable" or if 'Billing state' is "Not billed". The actual billing date. Mandatory.

 

 

Adding Additional Information to Cost Description - The Content Tab

 

This is where you can add more information about the cost. 

 

Collaborating on the Cost - The Genius Live! Tab

 

The Genius Live! tab provides a complete history of collaboration, modifications, approvals and revisions of the Cost. For more information please see the chapter "Collaborating with Genius Live!".

 

Attaching Files to a Cost - The Attachment Tab

 

This section allows for the attachment of external files, see "Manage file attachments" in the document management section for more details.

Users can attach files to the cost form to store any additional information pertaining to it. It is however recommended to store each significant file attachment as a single document in Geniusproject. This will allow users to distribute, publish, or manage access rights for any attached file independently.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img103

 

Linking Documents to a Cost - The Linked Documents Tab

 

This tab contains all of the links the cost has to other documents that are part of the project. Geniusproject offers the ability to save links between related project documents. For more information on this topic see the chapter "Linking documents".

 

Deleting a Cost

 

There are three possible ways to delete a cost:

  • Directly in Genius Planner if the cost was converted into a deliverable into a Gantt.
  • Directly from the Cost form. Click Delete on the menu action bar.
  • From a view. Select the cost(s) to be deleted and click Delete on the view menu action bar.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img104

 

 

The Labor Costs in the "Task" Document

 

The "Task" document is the description of a project task and includes the list of all associated assignments. It is not to be confused with the assignment document, which includes only one resource, and where the person assigned to the task enters their time spent. In the task, we find the elements linked to cost management. It is in this document that we can manage the following elements:

  • Activity type, which will determine the rate to apply in the case of multi-rate management.
  • Definition of a special resource rate for a task.
  • Specify whether the task’s billable amount is fixed or controlled.

In addition to these elements, the task includes the workload for each resource, and allows you to calculate the anticipated, actual, remaining and re-estimated costs by applying the rate associated to the resources.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img105

Activity type

Category that will determine the rate to apply in the event of multi-rate management.

The list of proposed values is issued from the "Keyword lists" setup document.

Billing Mode

The billing mode that applies to the task. Single selection field. Possible values are:

Not billable: nothing is billed.

Fixed price: the billing price is fixed in advance. It can be recorded through a Billing milestone.

Time and material: the billing price is based on time spent working on the task.

By default is inherited from projects billing mode.

Billing state

Not visible if "Billing mode" is set to "Not billable".

To indicate if the task is already billed or not. Single selection field. Possible values are:

Billed

Not billed

Partly billed

Cost
"Currency"

Indicates the initial, planned, actual, remaining and EAC (estimated at completion) costs. The currency is specified in the "General" setup document.

The cost is calculated automatically. It is composed of the sum of the costs for each resource assigned to the task, where the cost is obtained by multiplying the resource's rates by her/his workload.

See the "Tracking Costs and Budgets" for more information.

This fields are displayed in either of these cases:

the user belongs to the project team and has the "View Costs" role.

the user is not part of the resources excluded from seeing financial information, as defined in the "General" setup document.

the user is an application manager (i.e. has the "COP_MANAGERS" role).

The label is a shortcut opening a window displaying all costs in all available currencies defined in the "Other currencies" field of the "General" setup document.

Billable

Only visible if "Billing mode" is set to "Time spent".

Indicates the initial, planned, actual, remaining and EAC (estimated at completion) billable cost. The currency is specified in the "General" setup document.

The cost is calculated automatically. It is composed of the sum of the costs for each resource assigned to the task, where the cost is obtained by multiplying the resource's rates by her/his workload.

 

Tracking Costs and Budgets

 

Geniusproject provides a number of views and documents so organizations can track financial progress across projects.

Geniusproject is a flexible, open solution allowing users to create reports and views as needed. It is also possible to interface with external applications, such as an ERP.

 

The Views

 

The "Cost tracking" views, found under "Costs & Budgets" in [Projects] tab contextual navigation menu, contain the elements necessary to track project financial progress. They display forecasted, planned,, used and remaining budgets and allow for financial tracking of hours worked by resources, purchases and investments, margins and invoicing.

 

The Budget Tracking by Project View

 

This is one of the cost tracking views included with Geniusproject’s default setup. It consolidates information from budgets, assignments, timesheets and costs.

  • The "Budget" columns display values defined in forecasted budgets.
  • The "Planned" columns display values based on planned tasks and assignments.
  • The "Actual" columns display the values for actual time and costs.

The view consolidates information by project and cost type. If the budget is broken down by period then the information will be categorized by period, then project, then type.

The view provides a very detailed breakdown of labor and non-labor related costs and their differences from what was forecasted in the budget. The data in this view is only accurate if timesheets are being used.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img106

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img107Budget Value.

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img108Actual value from a timesheet line.

 

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img109Planned value for an assignment & Planned and actual values for a cost.

 

The Financial Indicators by Month View

 

This is one of the cost tracking views included with Geniusproject’s default setup. The values are pulled from the project overviews and displays financial indicators by month. The elements are added up at the project level, and at the top level, including sub-projects.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img110

This view provides a clear vision of the evolution of projects costs from month to month.

 

The Project Cost Tracking View

 

This is one of the cost tracking views included with Geniusproject’s default setup. It’s a simple configurable view that lists project tasks and costs with their forecasted/ planned and actual costs.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img111

 

 

The Project Cost Tracking by Phases View

 

This is one of the cost tracking views included with Geniusproject’s default setup.

This view shows financial information based on planned, actual and remaining workload as well planned, actual and billable amounts for non-labor related costs. These values come from project tasks and costs, and are displayed according to a project’s work breakdown structure (WBS). These elements are also added up at the project level, and at the top level, including sub-projects.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img112

This view is very useful in identifying time and costs that exceed the budget.

 

Cost Tracking Charts and Dashboards

 

Geniusproject includes several standard graphs and dashboard used for tracking costs, such as "Costs by month" available in the "Dashboard & Charts" contextual navigation menu from the [Projects] tab.

GP V7.2 User Manual_20131115 - CI_GI - 07-10_img113

 

 

 

 