Intro
Geniusproject offers a suite of robust project management tools that allow users to plan quick, small projects not requiring complex charts and features as well as more detailed projects and plans using the Genius Planner Gantt Charting tool. This section will focus on projects that are planned using a Gantt charting tool.
A Gantt chart is the ideal tool for successful visual communication of the project plan. It is a graphical representation of activity (task) development within a defined time frame as well as milestones (deliverables). It is used for the definition of tasks, for their duration and dependencies, and for communication between the different responsible parties. The Gantt chart is used to build a plan according to the following theoretical process:
-
Identify the deliverables (products of the project).
-
Identify the means to realize the deliverables (tasks).
-
Manage the links between the tasks and the deliverables.
-
Manage the delays.
-
Manage the resources (assignments).
In Geniusproject, the plan is the entry point for the creation of deliverables, tasks, management of delays and costs. The plan also allows for comparisons of actuals versus forecasts, to visualize eventual slippages and to react accordingly on the plan. The real dates (actual start date, remaining, etc.) are not captured in the plan, but in "task" and "deliverable" forms or in "timesheets" which are available to each of the project participa+nts. The dates reported by the project members are then updated in the project plan.
Each time a new project is created, its plan is automatically created with it.
To open your project’s Gantt chart:
-
Navigate to the Projects tab of the module bar.
-
Open Tasks & plans -> Plans-Gantt view.
-
Find your project in the list and click the "+" next to its name
-
Click Plan to open the Gantt in read mode, or right click Plan and select Edit to launch the Gantt in edit mode
Genius Planner is divided into multiple sections:
-
Window title containing the project name
-
Menu bar
-
Tool bar
-
Activities Table
-
Gantt Chart
-
Resource Table
-
Schedule diagram
You can reduce, expand or hide either of the sections by dragging the middle bar or using the twisties.
The Activity Table
The left side the activity table contains 10 columns:
# |
Row index. Static and cannot be modified. This column numbers the rows in the table. |
Name |
Activity name. One of the most important columns. It displays the hierarchy of phases, tasks and deliverables in the plan. All values can be modified except for the very first row, the "project name" which is generated automatically when the plan is created and cannot be modified. |
Resources |
Displays the external IDs for the resources assigned to an activity. External IDs for all resources assigned to the activity are listed. To edit the list, double-click in the cell to be edited and the Activity Properties Window dialog box will open. Assignments for this activity can be added, changed or deleted which in turn will update the list of external IDs displayed. Note: It is NOT possible to assign resources to a phase and a task cannot be converted into a phase by indenting or outdenting, if one or more assignments already exist for it.
|
Duration |
Activity duration. The duration of tasks can be changed directly in the "Duration" column, as long as the task is not completed or cancelled. This column is also useful to change a task into a deliverable by setting its value to "0". |
Start |
Activity start date. The start date of activities can be changed directly in the "Start" column, as long as the activity is NOT in progress, completed or cancelled. The date value can be changed more intuitively by using the small popup calendar available on the right-hand part of the cell. |
End |
Activity end date. Acting like the "Start" column, the end date of tasks can be changed directly in the "End" column, as long as the task is NOT completed or cancelled. The date value can also be changed by using the small popup calendar available on the right-hand part of the cell. |
Load |
Total workload for the task. This cell is NOT directly editable as this is the computed sum of all assignments. |
Predecessor |
Row number. Indicates if there are any dependencies between activities and displays the row number of the activities it is dependent upon. |
ID |
Activity ID. The "ID" column is not relevant to the user, however is mandatory for Genius Planner. This column contains a unique ID for each row. |
Columns widths can be resized by dragging the separation line between two columns. The height of all rows can be increased and decreased through the Action menu:
View -> Grids -> Activities Chart" and View -> Grids -> Assignments Chart.
The exact place where activities are created or pasted depends on the current row selection. Pasted or created tasks will be placed right after the last selected row in the activities table. The indentation level of this row will be inherited by the inserted tasks.
When pasting a group of activities containing phases, the indentation levels will be adapted accordingly. If no row is selected in the activities table, the pasted or created tasks will be appended to the end of the tasks list. This implies that these tasks will be on the first indentation level.
If a task needs to be moved within the plan hierarchy, the "Indent," "Outdent," "Move Up," and "Move Down" actions can be used to move it.
The Gantt Chart
The Gantt Chart is used to graphically display the project’s timeline including its phases, tasks, milestones and constraints.
The dynamic time scale at the top of the diagram can be used to scroll forward and back along the project timeline by clicking and holding directly on the time scale and scroll. The scroll bar at the bottom of the diagram can be used as well.
The time scale can also be used to zoom out, simply double click directly. Use the zoom icons on the toolbar to zoom back in.
The Gantt Chart is displayed in its default style named Blueberry. It is also possible to display it in the alternate style named Tangerine.
To change the Gantt style:
-
Navigate to the View menu
-
Select Style-> Tangerine
The elements used in the Gantt chart, in either style are:
|
Blueberry style |
Tangerine style |
Phases |
Black bar delimited by two black markers. |
Brown bar delimited by two brown markers. |
Tasks |
Blue bars. If a task is in progress, the percentage of progress will be displayed as a green bar on the task bar. Once progress reaches 100%, the entire task bar will turn green. If the task is marked as "Completed", then it will turn cyan. |
Orange bars. If a task is in progress, the percentage of progress will be displayed as a green bar on the task bar. Once progress reaches 100%, the entire task bar will turn green. If the task is marked as "Completed", then it will turn cyan. |
Milestones |
Blue diamond. If a milestone is completed, it will turn cyan. |
Orange diamond. If a milestone is completed, it will turn cyan. |
Critical path |
When the "Critical Path" is active, all critical tasks, milestones and constraints are displayed in red. Progression is still displayed, but in a darker tone of red |
When the "Critical Path" is active, all critical tasks, milestones and constraints are displayed in red. Progression is still displayed, but in a darker tone of red. |
The Genius planner Gantt chart offers various tools to organize your project plan. These tools are accessible from the toolbar and the menu options.
Menu Action |
Description |
Shortcut |
Read |
Edit |
Tool bar |
---|---|---|---|---|---|
Plan Menu |
|
|
P |
P |
|
Planned dates > |
3 options: •Show: Display the Gantt Chart with planned dates •Accept selected dates as planned dates: Save selected new changes to the project dates as planned dates •Accept all current dates as planned dates: Save all new changes to the project dates as planned dates |
|
|
P |
|
Initial baseline > |
3 options: •Show: Display the initial baseline in the Gantt Chart •Accept selected current dates as initial baseline: Save selected new changes into the initial baseline •Accept all current dates as initial baseline: Save all new changes into the initial baseline |
|
|
P |
|
Insert sub-project |
Insert an existing sub-project into the plan |
ALT-J |
|
P |
P |
Remove sub-project |
Remove a sub-project from the plan. The sub-project is NOT deleted. |
|
|
P |
P |
Edit |
Edit the current plan. |
CTRL-E |
P |
|
P |
Save > |
2 options: •Without closing: Saves the current version of the plan. In order to propagate all the changes in all records of the project, the plan is briefly closed and reopened in edit mode. •And close: Same as above, but the plan is closed after saving. |
CTRL-S
CTRL-SHIFT-S |
|
P |
P |
Save & Notify > |
2 options: •Without closing: Saves the current version of the plan and sends a notification to people listed in the distribution list. In order to propagate all the changes in all records of the project, the plan is briefly closed and reopened in edit mode. •And close: Same as above but the plan is closed after saving. |
CTRL-N
CTRL-SHIFT-N |
|
P |
|
Print… |
Open the print preview dialogue box to print either the Gantt or the Schedule chart. |
CTRL-P |
P |
P |
P |
Close Window |
Close the chart window, but not the plan document. The plan window can be reopened by clicking on the Genius Planner logo. |
CTRL-W |
P |
P |
P |
Edit Menu |
|
|
|
P |
|
Undo |
Undo the last action. |
CTRL-Z |
|
P |
P |
Redo |
Redo the last cancelled action. |
CTRL-Y |
|
P |
P |
Activity Menu |
|
|
P |
P |
|
Insert Activity |
Inserts a new task after the last selected task in the Gantt chart. The new task is appended at the end of the task list if no task is selected. It has a default name and duration of 1 day starting at the present date. |
INS |
|
P |
P |
Copy Activities |
Copies the selected activities to the clipboard. Assignments are copied without the current progress. Constraints are copied as well if they exist. The content of the clipboard is not readable outside of the Genius Planner context. |
CTRL-C |
|
P |
P |
Paste Activities |
Pastes tasks currently on the clipboard after the last selected task in the Gantt chart. Pasted tasks are appended at the end of the tasks list if no task is selected. |
CTRL-V |
|
P |
P |
Delete Activity |
Deletes the currently selected tasks in the Gantt chart. The user has to confirm this action before the operation is performed. |
DEL |
|
P |
P |
Progress > |
2 options: •Work: Display the standard work progress in activities. •Physical: Display the physical progress on activities and allow changing this value in the properties of activities. |
|
P |
P |
|
Activity Properties |
Opens the Activity Properties Window to the "General" section. |
CTRL-I |
P |
P |
P |
Edit Assignments |
Opens the "Activity Properties Window" to the "Resources" section. |
CTRL-R |
P |
P |
P |
Delete Assignments |
Deletes all assignments for the currently selected task in the Gantt chart. The user has to confirm his action before the operation is performed. |
CTRL-D |
|
P |
P |
Indent Activity |
Indents selected tasks to a lower hierarchy level. |
CTRL-RIGHT |
|
P |
P |
Outdent Activity |
Outdents selected tasks to a higher hierarchy level. |
CTRL-LEFT |
|
P |
P |
Move Activity Up |
Moves the selected task upwards. The hierarchy level is not changed. |
CTRL-UP |
|
P |
P |
Move Activity Down |
Moves the selected task downwards. The hierarchy level is not changed. |
CTRL-DOWN |
|
P |
P |
Timeshift Activities |
Shifts the selected tasks, milestones and phases to a new date specified by the user, the start date being kept on the same day of the week. |
CTRL-T |
|
P |
P |
Move To Activity |
Jumps to the selected activity and displays it in the Gantt Chart. |
|
P |
P |
P |
Link Menu |
|
|
P |
P |
|
Link Selected Activities |
|
CTRL-L |
|
P |
P |
Create Link |
Used to create dependencies between two tasks. When using this action, the cursor changes to a cross. The start and end points of the constraint have to be selected. |
CTRL-INS |
|
P |
P |
Delete Link |
Deletes the currently selected constraint in the Gantt chart. The user has to confirm this action before the operation is performed. |
CTRL-DEL |
|
P |
P |
Link properties |
When a link between two tasks is selected, displays detailed information about the link, such as time lag. |
CTRL-SHIFT-I |
P |
P |
P |
Automatic END-START lnk |
Allows all newly created tasks to be constrained with an END-START constraint. |
|
|
P |
|
No END-START link |
By default, no END-START constraint is created between newly created tasks. |
|
|
P |
|
View Menu |
|
|
P |
P |
|
Field > |
|
|
P |
P |
|
Name |
By default, displays the name of the task inside the task bar in the Gantt Chart. |
|
P |
P |
|
Resources |
Displays the resources assigned to the task inside the task bar in the Gantt Chart. |
|
P |
P |
|
Start Time |
Display the start date / time of the task inside the task bar in the Gantt Chart. |
|
P |
P |
|
End Time |
Display the end date / time of the task inside the task bar in the Gantt Chart. |
|
P |
P |
|
Date Format > |
|
|
P |
P |
|
Short Date |
By default, dates are displayed in a short format in the Start and End column of the Gantt table (ex.: 24.11.05). |
|
P |
P |
|
Medium Date |
Dates are displayed in a medium format in the Start and End column of the Gantt table (ex.: 24 Nov. 2005). |
|
P |
P |
|
Long Date |
Dates are displayed in a long format in the Start and End column of the Gantt table (i.e. 24. November 2005). |
|
P |
P |
|
Full Date |
Dates are displayed in a full format in the Start and End column of the Gantt table (i.e. Wednesday, 24. November 2005). |
|
P |
P |
|
Style > |
|
|
P |
P |
|
Blueberry |
Applies the default "blue" style to the Gantt and Schedule charts. |
|
P |
P |
|
Tangerine |
Applies the alternate "orange" style to the Gantt and Schedule charts. |
|
P |
P |
|
Grids > |
Allows users to customize the grid appearance in the Gantt and Schedule diagrams. |
|
P |
P |
|
Activities Chart > |
|
|
P |
P |
|
Increase 2 Pixels |
Increases height of rows by 2 pixels. |
CTRL-K |
P |
P |
|
Decrease 2 Pixels |
Decreases height of rows by 2 pixels. |
CTRL-L |
P |
P |
|
Show Vertical Grid |
Checked by default. |
|
P |
P |
|
Vertical Grid Color… |
|
|
P |
P |
|
Show Weekends |
Checked by default. |
|
P |
P |
|
Weekend Color... |
|
|
P |
P |
|
Show Horizontal Grid |
Checked by default. |
|
P |
P |
|
Horizontal Grid Color... |
|
|
P |
P |
|
Color Rows |
|
|
P |
P |
|
Even Row Color... |
|
|
P |
P |
|
Odd Row Color... |
|
|
P |
P |
|
Assignments Chart > |
|
|
P |
P |
|
Increase 2 Pixels |
Increases height of rows by 2 pixels. |
CTRL-SHIFT-K |
P |
P |
|
Decrease 2 Pixels |
Decreases height of rows by 2 pixels. |
CTRL-SHIFT-L |
P |
P |
|
Show Vertical Grid |
Checked by default. |
|
P |
P |
|
Vertical Grid Color... |
|
|
P |
P |
|
Show Weekends |
Checked by default. |
|
P |
P |
|
Weekend Color... |
|
|
P |
P |
|
Show Horizontal Grid |
Checked by default. |
|
P |
P |
|
Horizontal Grid Color... |
|
|
P |
P |
|
Color Rows |
|
|
P |
P |
|
Even Row Color... |
|
|
P |
P |
|
Odd Row Color... |
|
|
P |
P |
|
Expand/Collapse All |
|
CTRL-ENTER |
P |
P |
P |
Show/Hide Critical Path |
|
|
P |
P |
P |
Zoom in |
|
CTRL-NUM+ |
P |
P |
P |
Zoom out |
|
CTRL-NUM- |
P |
P |
P |
Zoom to fit |
|
CTRL-F |
P |
P |
P |
Help Menu |
|
|
P |
P |
|
About... |
Displays an information window about the Genius Planner version number and build number. |
F1 |
P |
P |
|
The Genius Planner Toolbar
Toolbar Action |
Icon |
Description |
Shortcut |
Read |
Edit |
---|---|---|---|---|---|
Insert Activity |
|
Inserts a new task after the last selected task in the Gantt chart. The new task is appended at the end of the tasks list if no task is selected. It has a default name (New entry #) and a duration of 1 day starting at the present date. |
INS |
|
P |
Delete Activity |
|
Deletes the currently selected tasks in the Gantt chart. The user must confirm this action before the operation is performed. |
DEL |
|
P |
Insert Resource |
|
Add a published resource to the list of available resources. It will be added in the field "Internal project team" of the corresponding "Project description" document the next time the plan is synchronized. |
ALT-R |
|
P |
Create Link |
|
To create a new dependency between two tasks. When using this action, the cursor changes to a cross. The start and end points of the constraint have to be selected. |
CTRL-INS |
|
P |
Delete Link |
|
Deletes the currently selected constraints in the Gantt chart. The user must confirm this action before the operation is performed. |
CTRL-DEL |
|
P |
Undo |
|
Undo the last action. |
CTRL-Z |
|
P |
Redo |
|
Redo the last undone action. |
CTRL-Y |
|
P |
Copy Activities |
|
Copies the selected activities on the clipboard. Assignments are copied without the current progress. Constraints are copied as well, if they exist. The content of the clipboard is not readable outside of the Genius Planner context. |
CTRL-C |
|
P |
Paste Activities |
|
Pastes tasks currently in the clipboard after the last selected task in the Gantt chart. Pasted tasks are appended at the end of the tasks list if no task is selected. |
CTRL-V |
|
P |
Activity Properties |
|
Opens the Activity Properties Window and displays the "General" section. |
CTRL-I |
P |
P |
Link properties |
|
Opens the Link Properties Window. |
CTRL-K |
P |
P |
Edit Assignments |
|
Opens the "Activity Properties Window" and displays the "Resources" section. |
CTRL-R |
|
P |
Delete Assignment |
|
Deletes all assignments of the currently selected task in the Gantt chart. The user must confirm his action before the operation is performed. |
CTRL-D |
|
P |
Indent Activity |
|
Indents selected tasks to a lower hierarchy level. |
CTRL-RIGHT |
|
P |
Outdent Activity |
|
Outdents selected tasks to a higher hierarchy level. |
CTRL-LEFT |
|
P |
Move Activity Up |
|
Moves the selected task upwards. The hierarchy level is not changed. |
CTRL-UP |
|
P |
Move Activity Down |
|
Moves the selected task downwards. The hierarchy level is not changed. |
CTRL-DOWN |
|
P |
Timeshift Activity |
|
Shifts the selected tasks, milestones and phases to a new date specified by the user, the start date being kept on the same day of the week. |
CTRL-T |
|
P |
Move To Activity |
|
Jumps to the selected activity and displays it in the Gantt Chart. |
|
|
P |
Expand/Collapse all |
|
Toggles between expanding and collapsing all phases. When a plan is opened for the first time, all phases are expanded. |
CTRL-ENTER |
P |
P |
Show / Hide Critical Path |
|
Shows or hides the critical path of the current plan. |
|
P |
P |
Zoom In |
|
Zooms in. |
CTRL-NUM+ |
P |
P |
Zoom Out |
|
Zooms out. |
CTRL-NUM- |
P |
P |
Zoom To Fit |
|
Adjusts the zoom so the entire plan fits within the width of the Gantt Chart window. |
CTRL-F |
P |
P |
|
|
Prints the Gantt or Schedule chart. See: "Printing a Genius Planner plan" for further information. |
CTRL-P |
P |
P |
Creating Activities - Phases, Tasks and Deliverables
An activity in Geniusproject can either become a phase, a task or a deliverable. To create and schedule tasks and deliverables in the Gantt chart, click on the activity in the table that you would like the new activity to be after, and click on the "Insert activity" icon on the toolbar. You can also press Insert on the keyboard. A new activity will be added to the table and chart.
To move an activity, click the Move up or "Move down"
icons.
Click the icon to indent and the
icon outdent an activity. Once an activity has items indented beneath it, it automatically becomes a phase.
Any activity with a duration of one day or more is a task. An activity with a duration of 0 days is a deliverable. The duration of a phase is the result of the durations of all activities beneath it (not necessarily the sum as some activities may occur in parallel); a phase cannot have a duration applied to it directly.
To schedule a task or deliverable, simply click on the task bar or deliverable diamond and drag it to the desired date.
To increase the duration for a task, click on the end of the task and drag it out to its new start or end date.
Task or deliverable dates can also be defined in the "Activity Properties" dialog box.
Activity Properties
The "Activity Properties" dialog box displays all parameters of the selected activity, as well as its assignments. The dialog box is composed of two tabs, the [General] tab and the [Resources] tab. Depending on how you open the window, either one of the tabs may be active.
- Navigate to the Activity menu and select Activity Properties
- The Activity Properties dialog box will open to the General tab

The General tab contains the following activity properties:
Name |
The name of the task or milestone. |
Duration |
The sum of all calendar days between the start and end dates. When the Deliverable checkbox is checked, the duration is set to '0'. This value is always expressed in days. When the duration is changed, the Actual Start Date and Actual End Date are automatically updated. |
Work Progress |
The percentage of progress based on the actual amount of work already spent on this task. For a milestone, this value is always "0". Once the milestone is completed the value is set to "100%". |
Planned Load |
The sum of all planned assignments to individuals in the Planned column of the [Resources] tab. |
EAC Load |
The EAC (Estimated at Completion) load is the sum of all individual EAC loads computed in the EAC column of the [Resources] tab. |
Initial Load |
The sum of all initial assignments to resources in the Initial column of the [Resources] tab |
Planned Start Date |
The date the task or milestone is scheduled to begin. This value can only be changed until the task is in progress. The menu option "Plan > Planned dates > Accept all current dates as planned dates" can update all planned start dates based on a more accurate forecast taking into account all actual dates already known in the project: When the Planned Start Date is changed, the duration is automatically updated. |
Planned End Date |
The date when the task or milestone is scheduled to end. This value can be changed until the task is completed or cancelled. The menu option "Plan > Planned dates > Accept all current dates as planned dates" can update all planned end dates based with a more accurate forecast taking into account all actual dates already known in the project. "Plan > Planned dates > Accept selected current dates as planned dates" has the same effect, but only tasks selected by the user prior to use the menu. When the Planned End Date is changed, the duration is automatically updated. |
Current Start Date |
This is a computed start date taking into account all actual dates already known in the project as well as task dependencies. At the beginning of the project, all current start dates are the same as planned start date. When the project is completed, all current start dates are the same as actual start dates. When the project is in progress, current start dates represent the most probable forecast based on actual dates where they are available and on planned dates where actual dates are not yet known. |
Current End Date |
This is a computed end date taking into account all actual dates already known in the project as well as tasks dependencies. At the beginning of the project, all current end dates are the same as planned end date. When the project is completed, all current end dates are the same as actual end dates. When the project is in progress, current end dates represent the most probable forecast based on actual dates where they are available and on planned dates where actual dates are not yet known. |
Actual Start Date |
The date work on the activity actually began. This value cannot be modified. |
Actual End date |
The date the task was marked completed. This value cannot be modified. |
Initial Start Date |
The start date of the last saved initial baseline. This value can only be modified from the menu "Plan > Initial baseline > Accept selected current dates as initial baseline" and "Plan > Initial baseline > Accept all current dates as initial baseline": |
Initial End Date |
The end date of the last saved current baseline. This value can only be changed from the menu "Plan > Initial baseline > Accept selected current dates as initial baseline" and "Plan > Initial baseline > Accept all current dates as initial baseline". |
Deliverable |
When selected, the activity is a deliverable. The duration is set to "0" and all date fields, except the Actual Start Date, are no longer editable. When an activity is a Deliverable, only the first row on the [Resources] tab is available as only a single person can be responsible for a Deliverable. |
Enable on weekend |
When selected, the tasks can be scheduled on weekends (Saturday and Sunday). Checking the "Enable on weekend" checkbox has an impact on the task Duration. |
Once a task or deliverable has been created, resources can be assigned directly to them. In Geniusproject, multiple resources can be assigned to a single task but only one resource can be assigned to a deliverable.
To assign a resource to a task or deliverable, double-click in the cell in the resources column for that particular activity, and the Activity Properties dialog box will open to the Resources tab.
The Resources Tab
This section contains all assignment information for the selected activity.
To assign a resource to the activity:
-
Click on a line in the resources column
-
Select the desired resource from the drop down list of resources included in the project
If the activity is a deliverable, users will only be able to add an assignment to the first row, all other rows will be grayed out.
The Resources tab captures the following information:
Delete |
This button is used to delete the resource from the list of assignees. The button is active only if the "Resources" column contains a name and if the Actual workload value is "0.000". |
Workload chart |
This button is display of the workflow chart for the corresponding resource. The button is only active only if the "Resources" column contains a value. |
Resources |
A dropdown list of resources available from the current plan. The cell is only editable if the Actual workload value is "0.000". Only resources included in the Participants section of the "Project Description" document AND who have a unique "External ID" will be available in the drop down list. |
Planned |
The planned workload for the given resource. This value can only be modified as long as the task is not completed or cancelled. It is possible for an individual user’s assignment (workload) to exceed the duration of the task. An alert will warn the user that the planned workload is greater than the duration and will offer the option to cancel or proceed. |
Actual |
The actual amount of time the resource has already spent on the task. |
Remaining |
The remaining workload for the resource. |
EAC |
Estimate At Completion is the sum of the Actual and Remaining workload. |
Initial |
The initial workload is the amount saved with the initial baseline. |
Unit |
The unit of measure for the assignments. It can be hours or days and is defined in the setup. |
Once assignments have been made, they can be seen in the Schedule chart at the bottom of the window.
Checking Resource Availability
The Schedule chart is composed of a Resources table on the right, and a Schedule diagram on the left. The schedule chart is used to display how workload and tasks are distributed across the project team. It allows project managers to quickly identify resource allocation conflicts and to easily resolve them by dragging & dropping to reassign tasks.
The Resource table is made up of four columns:
# |
Row index. The "#" column is static and cannot be modified. This column indexes the number of rows in the table. |
Name |
Resource name. |
Load |
Resource workload. Graphically displays a resource’s workload on each task they are assigned to. |
ID |
External ID. Displays the resource’s unique "External ID". The external ID must be defined in the Resource document in order for the resource to be available in Genius Planner. |
The resource list only includes the resources added to the participants section of the "Project description" document; however they can also be added directly from the Genius Planner interface, as long as they are predefined in the system.
Each time the plan is opened the list of resources is synchronized with the project resources listed in the Project Description, ensuring the list is always up-to-date. Resources added directly from the Genius Planner interface will be added to the Internal project team field of the corresponding Project description document the next time the plan is saved.
The schedule chart and Gantt Chart above are synchronized. When zooming in and out of the Gantt Chart, or moving activities around, the Schedule diagram changes as well.
The Gantt Chart’s horizontal scroll bar is synchronized with the Schedule chart and is used to scroll through both diagrams.
The Schedule diagram is a graphical representation of all assignments in the plan. These assignments are displayed as blue bars. The workload for each assignment is displayed inside the bar in a darker tone of blue.
If the duration of the workload is greater than the duration of the task, the bar is purple.
If assignments are overlapping, then they will be displayed in separate lines.
Milestones are always displayed as blue diamonds, and a vertical blue line indicates the current day.
A tooltip is available for each activity simply by hovering the mouse cursor over the assignment in the Schedule chart.
Assignments in the schedule chart can be re-assigned simply by dragging & dropping.
In the event that a resource has been double-booked and one of their assignments must be re-assigned; project managers can do so directly in the Schedule chart.
In the diagram below, Frank Moore has been assigned 100% to two tasks during the same time frame.
To re-assign one of Frank’s tasks:
-
Click on the task to be re-assigned
-
Drag it up or down to the resource it is being re-assigned to
-
The task will now be assigned to the new resource
The Workload chart is a color coded diagram displaying a selected resource’s workload across all projects they are assigned to, including all scheduled unavailablities.
The Workload Chart is a great tool to identify a resource’s allocation across all projects and whether they are over allocated or have any scheduling conflicts.
To open the Workload Chart, click on its tab in the Resource Table:
It is also possible to open the workload chart for a resource while assigning them to a task:
-
Open the Activity properties for a task
-
Click the workload icon next to the resource’s name and the Workload chart will launch. This allows project managers to check resource availability prior to confirming the assignment.
By default, there is no resource selected in the "Resource" dropdown list. As soon as a resource is selected, the availability of that resource is displayed.
The Workload chart displays the various unavailabilities for the selected resource.
-
Selected resource (1).
-
List of project for selected resource (2). The project names displayed in red are the project having a backlog (see below).
-
Color-coded workload reservation block (3).
Workload assignments from the current plan are automatically added to the diagram and the availability information.
Genius doesn’t automatically re-plan the workload, which should have been completed. However, it will display as a reminder the delayed workload, for instance in the figure above, the project "Test TaskUniqueID from template" has 5.5 days of backlog.
The days of the week that the resource works as well as their percentage of availability (known as the "Global Unavailabilities") are also visible in the diagram. These values are defined in the Resource document. Since this type of unavailability is recurring, it is only displayed within a limited time range. The Global Unavailabilities begin one month before the current date and end at the date of the latest assignment in the future, or at least three months after the current date.
The time scale (-axis) is synchronized with the time scale of the Gantt Chart. The Y-axis is dynamic and changes according to the data displayed.
Project Managers select their project teams while completing the project description form in v. They do so in advance of creating the project plan to ensure that resources are available to assign tasks to, directly from the Gantt chart.
However, in the event that a Project Manager is already in the process of creating a project plan and they need to replace already selected resources, or simply need to add new ones to their team, they can do so directly from the project plan.
To add a resource to your project team directly from the Gantt chart view:
-
Click on the Insert resource icon
on the tool bar
-
Select the new resource to add from the "Insert new resource" dialog box and click OK.
-
The new resource will be added to the list and available for task assignments
-
Click on the Replace resource icon
on the toolbar
-
In the Resource replacement dialog box that opens, select the resource to be replaced and the replacement resource:
-
Once the replacement resource has been selected, all assignments made to the replaced resource will be re-assigned to the replacement resource.
Planning Dates and Baselines
Using Baselines
Geniusproject allows a project manager to track iterations of their project’s dates. The initial dates saved when planning a project are referred to as the Initial Baseline. A project’s baseline is meant to be used as a point of comparison between what the project schedule was intended to be and what it actually is.
Project Dates in Genius Planner
Genius Planner tracks three types of project dates:
-
Initial
-
Planned
-
Current
The "Current" state of the project plan displays all plan dates as of the current moment. All tasks are displayed as blue bars and deliverables as blue diamonds.
The shaded green portion of the task bar represents actual time spent on a task.
Initial Baseline
The "Initial" baseline is used to keep track of the intended project schedule that was initially planned and saved.
To see a plan’s "Initial" baseline:
-
Click the Dates field from the toolbar
-
Select Current and Initial
The "Initial" baseline will be displayed as a thin turquoise line under the current blue tasks and deliverables, but not necessarily on the same dates.
The "Initial" baseline is not automatically saved the first time a project plan is saved. All updates or modifications made to the project plan after the "Initial" baseline has been saved will not automatically be added to it.
If project managers want to save the "Initial" baseline, or make changes to the project plan that need to be added to the "Initial" baseline after it has been saved, they can do so manually.
To add tasks and deliverables to an existing "Initial" baseline:
-
Open the project plan
-
Click the Plan menu
-
Select Initial baseline -> Accept all current dates as initial baseline
-
All blue tasks lines and "Initial" baseline turquoise lines will now line up on the same dates.
If a project manager only wants to include selected task and deliverable updates into the "Initial" baseline they can follow the same steps as above, but select Accept selected current dates as initial baseline.
Planned Dates versus Current Dates
Once the initial baseline for a project has been saved, all future modifications and updates to the project are stored as "Planned" dates. Planned dates are displayed when "Current and Planned" are selected from the "Dates" field on the plan toolbar.
The Current dates reflect what is going on at the moment, specifically any actual time posted against tasks. While the planned dates reflect any rescheduling of the plan after the initial baseline has been saved and does not include actuals.
The "Planned" dates are displayed as a thin purple line under the blue tasks and deliverables, but not necessarily on the same dates.
The "Current" dates are automatically saved every time the project plan is saved. All updates or modifications made to the project plan after the "Planned" dates has been saved will not automatically be added to it.
If a project manager makes changes to the project plan that need to be part of the "Planned" dates, they can do so manually.
To make all current dates part of the planned dates:
-
Open the project plan
-
Click the Plan menu
-
Select Planned dates -> Accept all current dates as planned dates"
Replanning a Project
Once a project plan has been completed, it is possible to go back to it as many times as needed to make any necessary changes.
To return to a project’s Gantt chart:
-
Navigate to the Projects tab
-
From the contextual navigation menu, select Tasks and plans -> Plans-Gantt
-
Find the project to be edited in the list and click the plus icon "+" beside its name to expand
-
The first option below the title will be Gantt, click on it to open the plan form and the Gantt chart will launch automatically
-
Only the Project Manager and Project Manager Substitute can make changes to the plan. It is important to note that:
-
Tasks that have not yet begun can be rescheduled to start and end at any time
-
Tasks with time already posted against them cannot be moved. Their end date can be changed but the start date cannot
-
Completed tasks cannot be changed
Additional Planning Options
At any time, a project manager can toggle to the plan form that the Genius Planner is embedded in, and define additional planning options for the project.
Options – Generation Options |
Automatic numbering of phases |
Numbering of the plan phases will be automatic |
|
First phase number |
By default the first phase will be number 1. However, this value van be changed manually here |
|
Notifications by e-mail |
Specify whether resources should receive e-mails notifying them, of their task assignments |
Task status |
Assigned |
The value in this field defines the status of tasks as soon as they are assigned. The default value is "Setup-General" which means that the value defined in the General setup document it what is being used. This value can be changed on a per project basis. The options are: •Requested •Stand-by •In progress •Setup-General (the default) |
|
Not assigned |
The value in this field defines the status of tasks that are not yet assigned. The default value is "Setup-General," which means that the value defined in the General setup document it what is being used. This value can be changed on a per project basis. The options are: •Requested •Stand-by •In progress •Setup-General (the default) |
Links
The concept of constraints (links or dependencies) in Geniusproject only exists in the Gantt Chart.
Links can be created between tasks, between deliverables and between tasks and deliverables. It is not possible to create links between phases, excluding certain exceptions, which are displayed in a very light gray so as not to interfere with other valid constraints. These gray exception constraints should be ignored, as they will automatically be removed once the plan is saved.
There are four types of links that can be created with the following rules:
-
END-START: the start date of the targeted task cannot be set to the same date or before the end date of the source task.
-
START-END: the end date of the targeted task cannot be set before the start date of the source task.
-
START-START: the start date of the targeted task cannot be set before the start date of the source task.
-
END-END: the end date of the targeted task cannot be set after the end date of the source task.
To create a link between two tasks, click the icon in the tool bar, then select the start or end of the task bar (depending on the kind of link you want to define) from which the link has to start from and drag it to the start or end of the task bar where the link has to end. Milestones can be linked too and are done so the same way.
Click the icon to open the Link properties dialog box. It contains all of the information related to the selected constraint.
The window is available in both read and edit mode.
From |
The source activity of the link. Not editable. |
To |
The target activity of the link. Not editable. |
Type |
The type of link between the two activities. Not editable. |
Timelag |
To indicate a timelag between the two activities. The timelag can also be negative. |
To delete a link, first click on it in the Gantt Chart to select, then click the icon on the tool bar and the link will be deleted.
A task is potentially critical if the interval between itself and the subsequent linked task is null. It becomes critical when it cannot be delayed without delaying the whole project. Therefore, any task with a planned end date equal to the end date of the project is critical.
The critical path is then a sequence of linked tasks whose intervals are zero. Clicking the icon in the tool bar will automatically highlight in red all tasks and milestones part of the critical path.
Importing an MS-Project Plan
Projects do not always just include an internal project team. Organizations collaborate with external team members all the time that may be using a different planning tool, such as Microsoft® Project. It is also common that prior to licensing Geniusproject, organizations may have already purchased Microsoft® Project. It is therefore critical that users are able to import existing Microsoft® Project files into Geniusproject to ensure a seamless transition to the application and flexible collaboration with all team members.
Importing an existing Microsoft® Project plan into Geniusproject only takes a few easy steps. Before you begin you must first have a copy of the Microsoft® Project plan to be imported, saved as XML.
To save a file as XML:
-
Open the plan in Microsoft® Project and select Save as
-
In the Save as window, save as XML Document
Once an XML copy of the plan is available from your computer:
- Navigate to the Projects] tab, Plans - Gantt view
- Click the Actions menu and select Import an MSP file in XML format in Genius Planner
-
In the newly displayed dialog box, specify which project the plan is for and click Browse to find the saved XML file
Exporting to an MS-Project Plan
It is not uncommon for project teams to extend outside an organization; this can be due to external consultants or to the client itself who plays a role in the execution of a project. In these instances it may be necessary to share project plans with individuals who do not have access to Geniusproject. To accommodate this situation, Geniusproject plans can be exported to Microsoft® Project.
To export a project plan:
-
Navigate to the Projects tab Plans - Gantt view
-
Find the project to be exported and open the plan document
-
Click the Actions menu and select Export to Microsoft Project
Planning Document Deletion Rules
The planning documents deletion rules were removed from the general setup of the Projects database, and are now hard-coded. The deletion rules for tasks and deliverables once a plan is deleted are now the following:
Tasks
The tasks with an actual workload different of zero are not deleted.
Otherwise the tasks are deleted when they are in one of the following statuses: Stand-by, Requested, Postponed or Cancelled.
A task "In progress" with no actual workload will then be kept.
Deliverables
The deliverables are deleted only when they are in one of the following generic statuses: Stand-by, To accomplish or Cancelled.
Comments