Help Center

The Project Plan and Gantt Chart

The Activity Table  The Gantt Chart 
The Genius Planner Action Menu The Genius Planner Toolbar
Creating Activities - Phases, Tasks and Deliverables Checking Resource Availability
The Schedule Chart The Workload Chart
Adding a Resource to your Team Replacing a Resource
Planning Dates and Baselines Re-planning a Project
Additional Planning Options Links
Displaying a Critical Path Importing an MS-Project Plan
Exporting to an MS-Project Plan  

 

Intro

Geniusproject offers a suite of robust project management tools that allow users to plan quick, small projects not requiring complex charts and features as well as more detailed projects and plans using the Genius Planner Gantt Charting tool. This section will focus on projects that are planned using a Gantt charting tool.

A Gantt chart is the ideal tool for successful visual communication of the project plan. It is a graphical representation of activity (task) development within a defined time frame as well as milestones (deliverables). It is used for the definition of tasks, for their duration and dependencies, and for communication between the different responsible parties. The Gantt chart is used to build a plan according to the following theoretical process:

  • Identify the deliverables (products of the project).
  • Identify the means to realize the deliverables (tasks).
  • Manage the links between the tasks and the deliverables.
  • Manage the delays.
  • Manage the resources (assignments).

In Geniusproject, the plan is the entry point for the creation of deliverables, tasks, management of delays and costs. The plan also allows for comparisons of actuals versus forecasts, to visualize eventual slippages and to react accordingly on the plan. The real dates (actual start date, remaining, etc.) are not captured in the plan, but in "task" and "deliverable" forms or in "timesheets" which are available to each of the project participa+nts. The dates reported by the project members are then updated in the project plan.

Each time a new project is created, its plan is automatically created with it.

To open your project’s Gantt chart:

  • Navigate to the Projects tab of the module bar.
  • Open Tasks & plans -> Plans-Gantt view.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img170

  • Find your project in the list and click the "+" next to its name
  • Click Plan to open the Gantt in read mode, or right click Plan and select Edit to launch the Gantt in edit mode

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img171

Note: The Genius Planner Gantt chart is embedded in a form titled "Plan" where additional planning options can be set. To learn more about these options see the section, "The Plan form’s planning options". 

Genius Planner is divided into multiple sections:

  • Window title containing the project name
  • Menu bar
  • Tool bar
  • Activities Table
  • Gantt Chart
  • Resource Table
  • Schedule diagram

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img172

You can reduce, expand or hide either of the sections by dragging the middle bar or using the twisties.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img173

 

The Activity Table

 

The left side the activity table contains 10 columns:

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img174

#

Row index. Static and cannot be modified. This column numbers the rows in the table.

Name

Activity name. One of the most important columns. It displays the hierarchy of phases, tasks and deliverables in the plan. All values can be modified except for the very first row, the "project name" which is generated automatically when the plan is created and cannot be modified.

Resources

Displays the external IDs for the resources assigned to an activity. External IDs for all resources assigned to the activity are listed. To edit the list, double-click in the cell to be edited and the Activity Properties Window dialog box will open. Assignments for this activity can be added, changed or deleted which in turn will update the list of external IDs displayed.

Note: It is NOT possible to assign resources to a phase and a task cannot be converted into a phase by indenting or outdenting, if one or more assignments already exist for it.

Duration

Activity duration. The duration of tasks can be changed directly in the "Duration" column, as long as the task is not completed or cancelled. This column is also useful to change a task into a deliverable by setting its value to "0".

Start

Activity start date. The start date of activities can be changed directly in the "Start" column, as long as the activity is NOT in progress, completed or cancelled. The date value can be changed more intuitively by using the small popup calendar available on the right-hand part of the cell.

End

Activity end date. Acting like the "Start" column, the end date of tasks can be changed directly in the "End" column, as long as the task is NOT completed or cancelled. The date value can also be changed by using the small popup calendar available on the right-hand part of the cell.

Load

Total workload for the task. This cell is NOT directly editable as this is the computed sum of all assignments.

Predecessor

Row number. Indicates if there are any dependencies between activities and displays the row number of the activities it is dependent upon.

ID

Activity ID. The "ID" column is not relevant to the user, however is mandatory for Genius Planner. This column contains a unique ID for each row.

Columns widths can be resized by dragging the separation line between two columns. The height of all rows can be increased and decreased through the Action menu:

View -> Grids -> Activities Chart" and View -> Grids -> Assignments Chart.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img175

The exact place where activities are created or pasted depends on the current row selection. Pasted or created tasks will be placed right after the last selected row in the activities table. The indentation level of this row will be inherited by the inserted tasks.

When pasting a group of activities containing phases, the indentation levels will be adapted accordingly. If no row is selected in the activities table, the pasted or created tasks will be appended to the end of the tasks list. This implies that these tasks will be on the first indentation level.

If a task needs to be moved within the plan hierarchy, the "Indent," "Outdent," "Move Up," and "Move Down" actions can be used to move it.

 

The Gantt Chart

 

The Gantt Chart is used to graphically display the project’s timeline including its phases, tasks, milestones and constraints.

The dynamic time scale at the top of the diagram can be used to scroll forward and back along the project timeline by clicking and holding directly on the time scale and scroll. The scroll bar at the bottom of the diagram can be used as well.

The time scale can also be used to zoom out, simply double click directly. Use the zoom icons on the toolbar to zoom back in.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img176

The Gantt Chart is displayed in its default style named Blueberry. It is also possible to display it in the alternate style named Tangerine.

To change the Gantt style:

  • Navigate to the View menu
  • Select Style-> Tangerine

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img177

 

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img178

The elements used in the Gantt chart, in either style are:

 

Blueberry style

Tangerine style

Phases

Black bar delimited by two black markers.

Brown bar delimited by two brown markers.

Tasks

Blue bars.

If a task is in progress, the percentage of progress will be displayed as a green bar on the task bar. Once progress reaches 100%, the entire task bar will turn green.

If the task is marked as "Completed", then it will turn cyan.

Orange bars.

If a task is in progress, the percentage of progress will be displayed as a green bar on the task bar. Once progress reaches 100%, the entire task bar will turn green.

If the task is marked as "Completed", then it will turn cyan.

Milestones

Blue diamond.

If a milestone is completed, it will turn cyan.

Orange diamond.

If a milestone is completed, it will turn cyan.

Critical path

When the "Critical Path" is active, all critical tasks, milestones and constraints are displayed in red. Progression is still displayed, but in a darker tone of red

When the "Critical Path" is active, all critical tasks, milestones and constraints are displayed in red. Progression is still displayed, but in a darker tone of red.

The Genius planner Gantt chart offers various tools to organize your project plan. These tools are accessible from the toolbar and the menu options.

 

The Genius Planner Action Menu

 

Menu Action

Description

Shortcut

Read
mode

Edit
mode

Tool bar

Plan Menu

 

 

P

P

 

Planned dates >

3 options:

Show: Display the Gantt Chart with planned dates

Accept selected dates as planned dates: Save selected new changes to the project dates as planned dates

Accept all current dates as planned dates: Save all new changes to the project dates as planned dates

 

 

P

 

Initial baseline >

3 options:

Show: Display the initial baseline in the Gantt Chart

Accept selected current dates as initial baseline: Save selected new changes into the initial baseline

Accept all current dates as initial baseline: Save all new changes into the initial baseline

 

 

P

 

Insert sub-project

Insert an existing sub-project into the plan

ALT-J

 

P

P

Remove sub-project

Remove a sub-project from the plan. The sub-project is NOT deleted.

 

 

P

P

Edit

Edit the current plan.

CTRL-E

P

 

P

Save >

2 options:

Without closing:  Saves the current version of the plan. In order to propagate all the changes in all records of the project, the plan is briefly closed and reopened in edit mode.

And close: Same as above, but the plan is closed after saving.

 

CTRL-S

 

 

 

CTRL-SHIFT-S

 

P

 

 

 

 

 

P

Save & Notify >

2 options:

Without closing:  Saves the current version of the plan and sends a notification to people listed in the distribution list. In order to propagate all the changes in all records of the project, the plan is briefly closed and reopened in edit mode.

And close:  Same as above but the plan is closed after saving.

CTRL-N

 

 

 

 

CTRL-SHIFT-N

 

P

 

Print…

Open the print preview dialogue box to print either the Gantt or the Schedule chart.

CTRL-P

P

P

P

Close Window

Close the chart window, but not the plan document. The plan window can be reopened by clicking on the Genius Planner logo.

CTRL-W

P

P

P

Edit Menu

 

 

 

P

 

Undo

Undo the last action.

CTRL-Z

 

P

P

Redo

Redo the last cancelled action.

CTRL-Y

 

P

P

Activity Menu

 

 

P

P

 

Insert Activity

Inserts a new task after the last selected task in the Gantt chart. The new task is appended at the end of the task list if no task is selected. It has a default name and duration of 1 day starting at the present date.

INS

 

P

P

Copy Activities

Copies the selected activities to the clipboard. Assignments are copied without the current progress. Constraints are copied as well if they exist.

The content of the clipboard is not readable outside of the Genius Planner context.

CTRL-C

 

P

P

Paste Activities

Pastes tasks currently on the clipboard after the last selected task in the Gantt chart. Pasted tasks are appended at the end of the tasks list if no task is selected.

CTRL-V

 

P

P

Delete Activity

Deletes the currently selected tasks in the Gantt chart.

The user has to confirm this action before the operation is performed.

DEL

 

P

P

Progress >

2 options:

Work: Display the standard work progress in activities.

Physical: Display the physical progress on activities and allow changing this value in the properties of activities.

 

P

P

 

Activity Properties

Opens the Activity Properties Window to the "General" section.

CTRL-I

P

P

P

Edit Assignments

Opens the "Activity Properties Window" to the "Resources" section.

CTRL-R

P

P

P

Delete Assignments

Deletes all assignments for the currently selected task in the Gantt chart.

The user has to confirm his action before the operation is performed.

CTRL-D

 

P

P

Indent Activity

Indents selected tasks to a lower hierarchy level.

CTRL-RIGHT

 

P

P

Outdent Activity

Outdents selected tasks to a higher hierarchy level.

CTRL-LEFT

 

P

P

Move Activity Up

Moves the selected task upwards. The hierarchy level is not changed.

CTRL-UP

 

P

P

Move Activity Down

Moves the selected task downwards. The hierarchy level is not changed.

CTRL-DOWN

 

P

P

Timeshift Activities

Shifts the selected tasks, milestones and phases to a new date specified by the user, the start date being kept on the same day of the week.

CTRL-T

 

P

P

Move To Activity

Jumps to the selected activity and displays it in the Gantt Chart.

 

P

P

P

Link Menu

 

 

P

P

 

Link Selected Activities

 

CTRL-L

 

P

P

Create Link

Used to create dependencies between two tasks. When using this action, the cursor changes to a cross. The start and end points of the constraint have to be selected.

CTRL-INS

 

P

P

Delete Link

Deletes the currently selected constraint in the Gantt chart.

The user has to confirm this action before the operation is performed.

CTRL-DEL

 

P

P

Link properties

When a link between two tasks is selected, displays detailed information about the link, such as time lag.

CTRL-SHIFT-I

P

P

P

Automatic END-START lnk

Allows all newly created tasks to be constrained with an END-START constraint.

 

 

P

 

No END-START link

By default, no END-START constraint is created between newly created tasks.

 

 

P

 

View Menu

 

 

P

P

 

Field >

 

 

P

P

 

Name

By default, displays the name of the task inside the task bar in the Gantt Chart.

 

P

P

 

Resources

Displays the resources assigned to the task inside the task bar in the Gantt Chart.

 

P

P

 

Start Time

Display the start date / time of the task inside the task bar in the Gantt Chart.

 

P

P

 

End Time

Display the end date / time of the task inside the task bar in the Gantt Chart.

 

P

P

 

Date Format >

 

 

P

P

 

Short Date

By default, dates are displayed in a short format in the Start and End column of the Gantt table (ex.: 24.11.05).

 

P

P

 

Medium Date

Dates are displayed in a medium format in the Start and End column of the Gantt table (ex.: 24 Nov. 2005).

 

P

P

 

Long Date

Dates are displayed in a long format in the Start and End column of the Gantt table (i.e. 24. November 2005).

 

P

P

 

Full Date

Dates are displayed in a full format in the Start and End column of the Gantt table (i.e. Wednesday, 24. November 2005).

 

P

P

 

Style >

 

 

P

P

 

Blueberry

Applies the default "blue" style to the Gantt and Schedule charts.

 

P

P

 

Tangerine

Applies the alternate "orange"  style to the Gantt and Schedule charts.

 

P

P

 

Grids >

Allows users to customize the grid appearance in the Gantt and Schedule diagrams.

 

P

P

 

Activities Chart >

 

 

P

P

 

Increase 2 Pixels

Increases height of rows by 2 pixels.

CTRL-K

P

P

 

Decrease 2 Pixels

Decreases height of rows by 2 pixels.

CTRL-L

P

P

 

Show Vertical Grid

Checked by default.

 

P

P

 

Vertical Grid Color…

 

 

P

P

 

Show Weekends        

Checked by default.

 

P

P

 

Weekend Color...

 

 

P

P

 

Show Horizontal Grid

Checked by default.

 

P

P

 

Horizontal Grid Color...

 

 

P

P

 

Color Rows

 

 

P

P

 

Even Row Color...

 

 

P

P

 

Odd Row Color...

 

 

P

P

 

Assignments Chart >

 

 

P

P

 

Increase 2 Pixels

Increases height of rows by 2 pixels.

CTRL-SHIFT-K

P

P

 

Decrease 2 Pixels

Decreases height of rows by 2 pixels.

CTRL-SHIFT-L

P

P

 

Show Vertical Grid

Checked by default.

 

P

P

 

Vertical Grid Color...

 

 

P

P

 

Show Weekends        

Checked by default.

 

P

P

 

Weekend Color...

 

 

P

P

 

Show Horizontal Grid

Checked by default.

 

P

P

 

Horizontal Grid Color...

 

 

P

P

 

Color Rows

 

 

P

P

 

Even Row Color...

 

 

P

P

 

Odd Row Color...

 

 

P

P

 

Expand/Collapse All

 

CTRL-ENTER

P

P

P

Show/Hide Critical Path

 

 

P

P

P

Zoom in

 

CTRL-NUM+

P

P

P

Zoom out

 

CTRL-NUM-

P

P

P

Zoom to fit

 

CTRL-F

P

P

P

Help Menu

 

 

P

P

 

About...

Displays an information window about the Genius Planner version number and build number.

F1

P

P

 

 

The Genius Planner Toolbar

 

Toolbar Action

Icon

Description

Shortcut

Read
mode

Edit
mode

Insert Activity

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img179

Inserts a new task after the last selected task in the Gantt chart. The new task is appended at the end of the tasks list if no task is selected. It has a default name (New entry #) and a duration of 1 day starting at the present date.

INS

 

P

Delete Activity

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img180

Deletes the currently selected tasks in the Gantt chart.

The user must confirm this action before the operation is performed.

DEL

 

P

Insert Resource

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img181

Add a published resource to the list of available resources. It will be added in the field "Internal project team" of the corresponding "Project description" document the next time the plan is synchronized.

ALT-R

 

P

Create Link

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img182

To create a new dependency between two tasks. When using this action, the cursor changes to a cross. The start and end points of the constraint have to be selected.

CTRL-INS

 

P

Delete Link

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img183

Deletes the currently selected constraints in the Gantt chart.

The user must confirm this action before the operation is performed.

CTRL-DEL

 

P

Undo

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img184

Undo the last action.

CTRL-Z

 

P

Redo

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img185

Redo the last undone action.

CTRL-Y

 

P

Copy Activities

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img186

Copies the selected activities on the clipboard. Assignments are copied without the current progress. Constraints are copied as well, if they exist.

The content of the clipboard is not readable outside of the Genius Planner context.

CTRL-C

 

P

Paste Activities

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img187

Pastes tasks currently in the clipboard after the last selected task in the Gantt chart. Pasted tasks are appended at the end of the tasks list if no task is selected.

CTRL-V

 

P

Activity Properties

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img188

Opens the Activity Properties Window and displays the "General" section.

CTRL-I

P

P

Link properties

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img189

Opens the Link Properties Window.

CTRL-K

P

P

Edit Assignments

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img190

Opens the "Activity Properties Window" and displays the "Resources" section.

CTRL-R

 

P

Delete Assignment

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img191

Deletes all assignments of the currently selected task in the Gantt chart.

The user must confirm his action before the operation is performed.

CTRL-D

 

P

Indent Activity

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img192

Indents selected tasks to a lower hierarchy level.

CTRL-RIGHT

 

P

Outdent Activity

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img193

Outdents selected tasks to a higher hierarchy level.

CTRL-LEFT

 

P

Move Activity Up        

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img194

Moves the selected task upwards. The hierarchy level is not changed.

CTRL-UP

 

P

Move Activity Down

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img195

Moves the selected task downwards. The hierarchy level is not changed.

CTRL-DOWN

 

P

Timeshift Activity

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img196

Shifts the selected tasks, milestones and phases to a new date specified by the user, the start date being kept on the same day of the week.

CTRL-T

 

P

Move To Activity

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img197

Jumps to the selected activity and displays it in the Gantt Chart.

 

 

P

Expand/Collapse all

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img198

Toggles between expanding and collapsing all phases. When a plan is opened for the first time, all phases are expanded.

CTRL-ENTER

P

P

Show / Hide Critical Path

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img199

Shows or hides the critical path of the current plan.

 

P

P

Zoom In

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img200

Zooms in.

CTRL-NUM+

P

P

Zoom Out

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img201

Zooms out.

CTRL-NUM-

P

P

Zoom To Fit

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img202

Adjusts the zoom so the entire plan fits within the width of the Gantt Chart window.

CTRL-F

P

P

Print

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img203

Prints the Gantt or Schedule chart. See: "Printing a Genius Planner plan" for further information.

CTRL-P

P

P

Creating Activities - Phases, Tasks and Deliverables

 

An activity in Geniusproject can either become a phase, a task or a deliverable. To create and schedule tasks and deliverables in the Gantt chart, click on the activity in the table that you would like the new activity to be after, and click on the "Insert activity" icon  GP V7.2 User Manual_20131115 - CI_GI - 01-06_img179 on the toolbar. You can also press Insert on the keyboard. A new activity will be added to the table and chart.

 

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img205

To move an activity, click the Move up GP V7.2 User Manual_20131115 - CI_GI - 01-06_img194 or "Move down" GP V7.2 User Manual_20131115 - CI_GI - 01-06_img195 icons.

Click the  GP V7.2 User Manual_20131115 - CI_GI - 01-06_img192 icon to indent and the GP V7.2 User Manual_20131115 - CI_GI - 01-06_img193 icon outdent an activity. Once an activity has items indented beneath it, it automatically becomes a phase.

Any activity with a duration of one day or more is a task. An activity with a duration of 0 days is a deliverable. The duration of a phase is the result of the durations of all activities beneath it (not necessarily the sum as some activities may occur in parallel); a phase cannot have a duration applied to it directly.

To schedule a task or deliverable, simply click on the task bar or deliverable diamond and drag it to the desired date.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img210

To increase the duration for a task, click on the end of the task and drag it out to its new start or end date.

 

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img211

Task or deliverable dates can also be defined in the "Activity Properties" dialog box. 

 

Activity Properties

 

The "Activity Properties" dialog box displays all parameters of the selected activity, as well as its assignments. The dialog box is composed of two tabs, the [General] tab and the [Resources] tab. Depending on how you open the window, either one of the tabs may be active.

  • Navigate to the Activity menu and select Activity Properties
  • The Activity Properties dialog box will open to the General tab

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img212

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img213

Note: It is also possible to open the dialog box by double-clicking in the Resources column of the Activity table in the Gantt chart, or by clicking the GP V7.2 User Manual_20131115 - CI_GI - 01-06_img188 icon on the toolbar.
 
The General Tab
 

The General tab contains the following activity properties:

Name

The name of the task or milestone.

Duration

The sum of all calendar days between the start and end dates. When the Deliverable checkbox is checked, the duration is set to '0'. This value is always expressed in days.

When the duration is changed, the Actual Start Date and Actual End Date are automatically updated.

Work Progress

The percentage of progress based on the actual amount of work already spent on this task. For a milestone, this value is always "0". Once the milestone is completed the value is set to "100%".

Planned Load

The sum of all planned assignments to individuals in the Planned column of the [Resources] tab.

EAC Load

The EAC (Estimated at Completion) load is the sum of all individual EAC loads computed in the EAC column of the [Resources] tab.

Initial Load

The sum of all initial assignments to resources in the Initial column of the [Resources] tab

Planned Start Date

The date the task or milestone is scheduled to begin. This value can only be changed until the task is in progress.

The menu option "Plan > Planned dates > Accept all current dates as planned dates" can update all planned start dates based on a more accurate forecast taking into account all actual dates already known in the project:

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img215

When the Planned Start Date is changed, the duration is automatically updated.

Planned End Date

The date when the task or milestone is scheduled to end. This value can be changed until the task is completed or cancelled.

The menu option "Plan > Planned dates > Accept all current dates as planned dates" can update all planned end dates based with a more accurate forecast taking into account all actual dates already known in the project.

"Plan > Planned dates > Accept selected current dates as planned dates" has the same effect, but only tasks selected by the user prior to use the menu.

When the Planned End Date is changed, the duration is automatically updated.

Current Start Date

This is a computed start date taking into account all actual dates already known in the project as well as task dependencies.

At the beginning of the project, all current start dates are the same as planned start date.

When the project is completed, all current start dates are the same as actual start dates.

When the project is in progress, current start dates represent the most probable forecast based on actual dates where they are available and on planned dates where actual dates are not yet known.

Current End Date

This is a computed end date taking into account all actual dates already known in the project as well as tasks dependencies.

At the beginning of the project, all current end dates are the same as planned end date.

When the project is completed, all current end dates are the same as actual end dates.

When the project is in progress, current end dates represent the most probable forecast based on actual dates where they are available and on planned dates where actual dates are not yet known.

Actual Start Date

The date work on the activity actually began. This value cannot be modified.

Actual End date

The date the task was marked completed. This value cannot be modified.

Initial Start Date

The start date of the last saved initial baseline. This value can only be modified from the menu "Plan > Initial baseline > Accept selected current dates as initial baseline" and "Plan > Initial baseline > Accept all current dates as initial baseline":

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img216

Initial End Date

The end date of the last saved current baseline. This value can only be changed from the menu "Plan > Initial baseline > Accept selected current dates as initial baseline" and "Plan > Initial baseline > Accept all current dates as initial baseline".

Deliverable

When selected, the activity is a deliverable. The duration is set to "0" and all date fields, except the Actual Start Date, are no longer editable.

When an activity is a Deliverable, only the first row on the [Resources] tab is available as only a single person can be responsible for a Deliverable.

Enable on weekend

When selected, the tasks can be scheduled on weekends (Saturday and Sunday).

Checking the "Enable on weekend" checkbox has an impact on the task Duration.

 
Assigning Resources to an Activity
 

Once a task or deliverable has been created, resources can be assigned directly to them. In Geniusproject, multiple resources can be assigned to a single task but only one resource can be assigned to a deliverable.

To assign a resource to a task or deliverable, double-click in the cell in the resources column for that particular activity, and the Activity Properties dialog box will open to the Resources tab. 

 

The Resources Tab

 
This section contains all assignment information for the selected activity.

To assign a resource to the activity:

  • Click on a line in the resources column
  • Select the desired resource from the drop down list of resources included in the project

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img217

If the activity is a deliverable, users will only be able to add an assignment to the first row, all other rows will be grayed out.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img218

The Resources tab captures the following information:

Delete

This button is used to delete the resource from the list of assignees.

The button is active only if the "Resources" column contains a name and if the Actual workload value is "0.000".

Workload chart

This button is display of the workflow chart for the corresponding resource.

The button is only active only if the "Resources" column contains a value.

Resources

A dropdown list of resources available from the current plan.

The cell is only editable if the Actual workload value is "0.000".

Only resources included in the Participants section of the "Project Description" document AND who have a unique "External ID" will be available in the drop down list.

Planned

The planned workload for the given resource. This value can only be modified as long as the task is not completed or cancelled.

It is possible for an individual user’s assignment (workload) to exceed the duration of the task. An alert will warn the user that the planned workload is greater than the duration and will offer the option to cancel or proceed.

Actual

The actual amount of time the resource has already spent on the task.

Remaining

The remaining workload for the resource.

EAC

Estimate At Completion is the sum of the Actual and Remaining workload.

Initial

The initial workload is the amount saved with the initial baseline.

Unit

The unit of measure for the assignments. It can be hours or days and is defined in the setup.

Once assignments have been made, they can be seen in the Schedule chart at the bottom of the window. 

 

Checking Resource Availability

 

The Schedule chart is composed of a Resources table on the right, and a Schedule diagram on the left. The schedule chart is used to display how workload and tasks are distributed across the project team. It allows project managers to quickly identify resource allocation conflicts and to easily resolve them by dragging & dropping to reassign tasks.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img219

 

The Resource Table
 

The Resource table is made up of four columns:

#

Row index. The "#" column is static and cannot be modified. This column indexes the number of rows in the table.

Name

Resource name.

Load

Resource workload. Graphically displays a resource’s workload on each task they are assigned to.

ID

External ID. Displays the resource’s unique "External ID". The external ID must be defined in the Resource document in order for the resource to be available in Genius Planner.

The resource list only includes the resources added to the participants section of the "Project description" document; however they can also be added directly from the Genius Planner interface, as long as they are predefined in the system.

Each time the plan is opened the list of resources is synchronized with the project resources listed in the Project Description, ensuring the list is always up-to-date. Resources added directly from the Genius Planner interface will be added to the Internal project team field of the corresponding Project description document the next time the plan is saved.

 
The Schedule Chart
 

The schedule chart and Gantt Chart above are synchronized. When zooming in and out of the Gantt Chart, or moving activities around, the Schedule diagram changes as well.

The Gantt Chart’s horizontal scroll bar is synchronized with the Schedule chart and is used to scroll through both diagrams.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img220

The Schedule diagram is a graphical representation of all assignments in the plan. These assignments are displayed as blue bars. The workload for each assignment is displayed inside the bar in a darker tone of blue.

If the duration of the workload is greater than the duration of the task, the bar is purple.

If assignments are overlapping, then they will be displayed in separate lines.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img221

Milestones are always displayed as blue diamonds, and a vertical blue line indicates the current day.

A tooltip is available for each activity simply by hovering the mouse cursor over the assignment in the Schedule chart.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img222

Assignments in the schedule chart can be re-assigned simply by dragging & dropping.

In the event that a resource has been double-booked and one of their assignments must be re-assigned; project managers can do so directly in the Schedule chart.

In the diagram below, Frank Moore has been assigned 100% to two tasks during the same time frame.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img223

To re-assign one of Frank’s tasks:

  • Click on the task to be re-assigned
  • Drag it up or down to the resource it is being re-assigned to

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img224

  • The task will now be assigned to the new resource

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img225

 
The Workload Chart
 

The Workload chart is a color coded diagram displaying a selected resource’s workload across all projects they are assigned to, including all scheduled unavailablities.

The Workload Chart is a great tool to identify a resource’s allocation across all projects and whether they are over allocated or have any scheduling conflicts.

To open the Workload Chart, click on its tab in the Resource Table:

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img226

It is also possible to open the workload chart for a resource while assigning them to a task:

  • Open the Activity properties for a task
  • Click the workload icon next to the resource’s name and the Workload chart will launch. This allows project managers to check resource availability prior to confirming the assignment.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img227

By default, there is no resource selected in the "Resource" dropdown list. As soon as a resource is selected, the availability of that resource is displayed.

Note: This operation can take several seconds, depending of the amount of data that needs to be returned.

 

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img228

The Workload chart displays the various unavailabilities for the selected resource.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img229

  • Selected resource (1).
  • List of project for selected resource (2). The project names displayed in red are the project having a backlog (see below).
  • Color-coded workload reservation block (3).

Workload assignments from the current plan are automatically added to the diagram and the availability information.

Genius doesn’t automatically re-plan the workload, which should have been completed. However, it will display as a reminder the delayed workload, for instance in the figure above, the project "Test TaskUniqueID from template" has 5.5 days of backlog.

The days of the week that the resource works as well as their percentage of availability (known as the "Global Unavailabilities") are also visible in the diagram. These values are defined in the Resource document. Since this type of unavailability is recurring, it is only displayed within a limited time range. The Global Unavailabilities begin one month before the current date and end at the date of the latest assignment in the future, or at least three months after the current date.

The time scale (-axis) is synchronized with the time scale of the Gantt Chart. The Y-axis is dynamic and changes according to the data displayed.

 

Adding a Resource to your Team 
 

Project Managers select their project teams while completing the project description form in v. They do so in advance of creating the project plan to ensure that resources are available to assign tasks to, directly from the Gantt chart.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img230

However, in the event that a Project Manager is already in the process of creating a project plan and they need to replace already selected resources, or simply need to add new ones to their team, they can do so directly from the project plan.

To add a resource to your project team directly from the Gantt chart view:

  • Click on the Insert resource icon  GP V7.2 User Manual_20131115 - CI_GI - 01-06_img181 on the tool bar
  • Select the new resource to add from the "Insert new resource" dialog box and click OK.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img232

  • The new resource will be added to the list and available for task assignments
 
Replacing a Resource
 
To replace a project team member you must first make sure that the replacement resource has already been added to the project team. Next:
  • Click on the Replace resource icon  GP V7.2 User Manual_20131115 - CI_GI - 01-06_img233 on the toolbar
  • In the Resource replacement dialog box that opens, select the resource to be replaced and the replacement resource:

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img234

  • Once the replacement resource has been selected, all assignments made to the replaced resource will be re-assigned to the replacement resource.

 

Planning Dates and Baselines

 

Using Baselines

 

Geniusproject allows a project manager to track iterations of their project’s dates. The initial dates saved when planning a project are referred to as the Initial Baseline. A project’s baseline is meant to be used as a point of comparison between what the project schedule was intended to be and what it actually is.

 

Project Dates in Genius Planner

 

Genius Planner tracks three types of project dates:

  • Initial
  • Planned
  • Current

The "Current" state of the project plan displays all plan dates as of the current moment. All tasks are displayed as blue bars and deliverables as blue diamonds.

The shaded green portion of the task bar represents actual time spent on a task.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img235

 

Initial Baseline

 

The "Initial" baseline is used to keep track of the intended project schedule that was initially planned and saved.

To see a plan’s "Initial" baseline:

  • Click the Dates field from the toolbar
  • Select Current and Initial

The "Initial" baseline will be displayed as a thin turquoise line under the current blue tasks and deliverables, but not necessarily on the same dates.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img236

The "Initial" baseline is not automatically saved the first time a project plan is saved. All updates or modifications made to the project plan after the "Initial" baseline has been saved will not automatically be added to it.

If project managers want to save the "Initial" baseline, or make changes to the project plan that need to be added to the "Initial" baseline after it has been saved, they can do so manually.

To add tasks and deliverables to an existing "Initial" baseline:

  • Open the project plan
  • Click the Plan menu
  • Select Initial baseline -> Accept all current dates as initial baseline

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img216

  • All blue tasks lines and "Initial" baseline turquoise lines will now line up on the same dates.

If a project manager only wants to include selected task and deliverable updates into the "Initial" baseline they can follow the same steps as above, but select Accept selected current dates as initial baseline.

 

Planned Dates versus Current Dates

 

Once the initial baseline for a project has been saved, all future modifications and updates to the project are stored as "Planned" dates. Planned dates are displayed when "Current and Planned" are selected from the "Dates" field on the plan toolbar.

The Current dates reflect what is going on at the moment, specifically any actual time posted against tasks. While the planned dates reflect any rescheduling of the plan after the initial baseline has been saved and does not include actuals.

The "Planned" dates are displayed as a thin purple line under the blue tasks and deliverables, but not necessarily on the same dates.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img238

The "Current" dates are automatically saved every time the project plan is saved. All updates or modifications made to the project plan after the "Planned" dates has been saved will not automatically be added to it.

If a project manager makes changes to the project plan that need to be part of the "Planned" dates, they can do so manually.

To make all current dates part of the planned dates:

  • Open the project plan
  • Click the Plan menu
  • Select Planned dates -> Accept all current dates as planned dates"

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img215

 

Replanning a Project

 

Once a project plan has been completed, it is possible to go back to it as many times as needed to make any necessary changes.

To return to a project’s Gantt chart:

  • Navigate to the Projects tab
  • From the contextual navigation menu, select Tasks and plans -> Plans-Gantt
  • Find the project to be edited in the list and click the plus icon "+" beside its name to expand
  • The first option below the title will be Gantt, click on it to open the plan form and the Gantt chart will launch automatically
  • Only the Project Manager and Project Manager Substitute can make changes to the plan. It is important to note that:
    • Tasks that have not yet begun can be rescheduled to start and end at any time
    • Tasks with time already posted against them cannot be moved. Their end date can be changed but the start date cannot
    • Completed tasks cannot be changed

 

Additional Planning Options

 

At any time, a project manager can toggle to the plan form that the Genius Planner is embedded in, and define additional planning options for the project.

Options – Generation Options

Automatic numbering of phases

Numbering of the plan phases will be automatic

 

First phase number

By default the first phase will be number 1. However, this value van be changed manually here

 

Notifications by e-mail

Specify whether resources should receive e-mails notifying them, of their task assignments

Task status

Assigned

The value in this field defines the status of tasks as soon as they are assigned. The default value is "Setup-General" which means that the value defined in the General setup document it what is being used. This value can be changed on a per project basis. The options are:

Requested

Stand-by

In progress

Setup-General (the default)

 

Not assigned

The value in this field defines the status of tasks that are not yet assigned. The default value is "Setup-General," which means that the value defined in the General setup document it what is being used. This value can be changed on a per project basis. The options are:

Requested

Stand-by

In progress

Setup-General (the default)

 

 

Links

 

The concept of constraints (links or dependencies) in Geniusproject only exists in the Gantt Chart.

Links can be created between tasks, between deliverables and between tasks and deliverables. It is not possible to create links between phases, excluding certain exceptions, which are displayed in a very light gray so as not to interfere with other valid constraints. These gray exception constraints should be ignored, as they will automatically be removed once the plan is saved.

There are four types of links that can be created with the following rules:

  • END-START: the start date of the targeted task cannot be set to the same date or before the end date of the source task.
  • START-END: the end date of the targeted task cannot be set before the start date of the source task.
  • START-START: the start date of the targeted task cannot be set before the start date of the source task.
  • END-END: the end date of the targeted task cannot be set after the end date of the source task.
Note: The rules apply to tasks bound by constraints that are not yet in progress, completed or cancelled.
 
Creating a Link 

To create a link between two tasks, click the GP V7.2 User Manual_20131115 - CI_GI - 01-06_img240 icon in the tool bar, then select the start or end of the task bar (depending on the kind of link you want to define) from which the link has to start from and drag it to the start or end of the task bar where the link has to end. Milestones can be linked too and are done so the same way.

 
Link Properties
 

Click the GP V7.2 User Manual_20131115 - CI_GI - 01-06_img189 icon to open the Link properties dialog box. It contains all of the information related to the selected constraint.

The window is available in both read and edit mode.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img242

From

The source activity of the link. Not editable.

To

The target activity of the link. Not editable.

Type

The type of link between the two activities. Not editable.

Timelag

To indicate a timelag between the two activities. The timelag can also be negative.

 
 
Deleting a Link

 

To delete a link, first click on it in the Gantt Chart to select, then click the GP V7.2 User Manual_20131115 - CI_GI - 01-06_img183 icon on the tool bar and the link will be deleted. 

 
Displaying a Critical Path

 

A task is potentially critical if the interval between itself and the subsequent linked task is null. It becomes critical when it cannot be delayed without delaying the whole project. Therefore, any task with a planned end date equal to the end date of the project is critical.

The critical path is then a sequence of linked tasks whose intervals are zero. Clicking the  GP V7.2 User Manual_20131115 - CI_GI - 01-06_img199  icon in the tool bar will automatically highlight in red all tasks and milestones part of the critical path.

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img245

 

 

Importing an MS-Project Plan

 

Projects do not always just include an internal project team. Organizations collaborate with external team members all the time that may be using a different planning tool, such as Microsoft® Project. It is also common that prior to licensing Geniusproject, organizations may have already purchased Microsoft® Project. It is therefore critical that users are able to import existing Microsoft® Project files into Geniusproject to ensure a seamless transition to the application and flexible collaboration with all team members.

Importing an existing Microsoft® Project plan into Geniusproject only takes a few easy steps. Before you begin you must first have a copy of the Microsoft® Project plan to be imported, saved as XML.

To save a file as XML:

  • Open the plan in Microsoft® Project and select Save as
  • In the Save as window, save as  XML Document

 

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img246

Once an XML copy of the plan is available from your computer:

  • Navigate to the Projects] tab, Plans - Gantt view
  • Click the Actions menu and select Import an MSP file in XML format in Genius Planner

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img247

  • In the newly displayed dialog box, specify which project the plan is for and click Browse to find the saved XML file

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img248

 

Exporting to an MS-Project Plan

 

It is not uncommon for project teams to extend outside an organization; this can be due to external consultants or to the client itself who plays a role in the execution of a project. In these instances it may be necessary to share project plans with individuals who do not have access to Geniusproject. To accommodate this situation, Geniusproject plans can be exported to Microsoft® Project.

Note: For this feature to be possible the user receiving the exported file must have Microsoft® Project installed on their machine.

To export a project plan:

  • Navigate to the Projects tab Plans - Gantt view
  • Find the project to be exported and open the plan document
  • Click the Actions menu and select Export to Microsoft Project

GP V7.2 User Manual_20131115 - CI_GI - 01-06_img249

 

Planning Document Deletion Rules

 

The planning documents deletion rules were removed from the general setup of the Projects database, and are now hard-coded. The deletion rules for tasks and deliverables once a plan is deleted are now the following:

Tasks

The tasks with an actual workload different of zero are not deleted.

Otherwise the tasks are deleted when they are in one of the following statuses: Stand-by, Requested, Postponed or Cancelled.

A task "In progress" with no actual workload will then be kept.

Deliverables

The deliverables are deleted only when they are in one of the following generic statuses: Stand-by, To accomplish or Cancelled.

Have more questions? Submit a request

Comments