Note: Errors displayed in bold are recurring errors, or errors reported at least by two different sources. Errors considered as critical errors are displayed in red.
Modules
Additional Fields
Ref. # |
Title |
5108 |
Ampersand not managed in additional fields. |
5110 |
Switch button in additional fields show wrong value in read mode. |
5285 |
Internet Explorer 11: Additional field columns do not show up in the view. |
5286 |
When deleting additional field setup documents, the columns are not removed from the view |
4942 |
Additional field columns are not added to configurable views for deliverables, change requests and IT tickets. |
5095 |
Impossible to create additional fields for progress reports. |
Budget
Ref. # |
Title |
5417 |
Budget Grid header shows French text. |
5242 |
When a project request is promoted to a project, the budget lines are not copied along. |
4869 |
Issues on detailed budgets when OBS is an axis. |
5080 |
OBS readers are not propagated in the Budget while creating a new project. |
5065 |
Sometimes, the budget lines are not retrieved in the budget. |
Charts
Ref. # |
Title |
5129 |
Charts are not available on smartphones and tablets. |
4716 |
JavaScript error when loading charts and reports. |
3224 |
Charts setup: Impossible to select view names. |
5082 |
Some totals are wrong in availability/workload charts. |
5354 |
Avoid JavaScript error when opening charts in the Notes client. |
4938 |
Dashboard setup form displays are all broken. |
5319 |
JavaScript error when opening a saved chart. |
5172 |
Impossible to open a chart from a document. |
5304 |
Error when saving charts. |
Configurable Views
Ref. # |
Title |
5389 |
Projects - Configurable view systematically crashes the Domino Server when accessed by a Reader user. |
5200 |
Configurable views not loading after ungrouping the main category column. |
4976 |
Coloration is not applied to totals in configurable views. |
5237 |
Exporting to Excel shows empty categories. |
4428 |
Sub-projects in the configurable views begin with '…' so they always are at the beginning or the end of the list. |
4766 |
Missing data in the Projects costs view (Costs and assignments - Configurable view). |
5050 |
Configurable view scroll moves back to the top when opening a document in read mode. |
5208 |
Project overviews configurable view - Progress value is always 0. |
5125 |
Project status column is empty in the budget lines configurable view. |
5211 |
The Period column is always empty in some configurable views. |
5213 |
Default cost rate does not show in the Resources view. |
5204 |
Reader users should not see the 'Resources' menu in the projects views. |
5197 |
System events with agent MigrateJSONDocuments. |
5353 |
Fields not loading in Soft Booking view. |
5456 |
The OBS subject is not saved if the project is not saved after the wizard generation. |
5469 |
The project overview configurable view shows archived versions. |
5398 |
Configurable views are missing in right-click Edit menu. |
4844 |
Deleting a task from a configurable view does not prompt the user if the documents cannot be deleted. |
4980 |
Deleting several selected records from a configurable view only deletes the first selected record. |
5069 |
Some configurable views cannot be opened after a version update. |
5166 |
Refresh button not working in some configurable views. |
4975 |
Time input from the stopwatch menu is not working in 'Assignments - To accomplish - Configurable view'. |
5333 |
The link to the Task in the view 'Time details - by week - configurable' does not work. |
4997 |
Wrong calculation in configurable view totals. |
5330 |
Hide cost information in configurable views for users without the appropriate role. |
5367 |
Odd things displayed in Excel Export from grouped configurable views with totals. |
5073 |
Inconsistency in the naming of the columns in the e-mail inbox view. |
4882 |
Resources - Configurable view: impossible to isolate only material resources. |
4977 |
Some configurable views do not exclude save conflicts, so they show as duplicate entries. |
4957 |
E-mails do appear in the Deliverable configurable view. |
5201 |
Projects overviews - Configurable views: the 'Project status' column is empty. |
5239 |
Numeric columns containing numbers greater than 1000 will be exported as 1,000. |
Documents
Ref. # |
Title |
5322 |
Error 'Item Body already exists' when converting a deliverable. |
4945 |
To Dos: actions Complete/Request again are not working properly. |
5022 |
Error message when creating a document in Internet Explorer 11. |
5087 |
Genius Integrator ActiveX: unknown publisher when trying to install. |
4851 |
Internet Explorer 9: Rich text field content is lost when editing Meeting minutes. |
5207 |
Some issues with regional settings 'Dutch (Netherlands)'. |
5173 |
Opening the search from the shortcut brings up the validation message. |
4991 |
The version number is not visible in the 'Incoming links' section. |
E-mails
Ref. # |
Title |
5075 |
Filing not working as specified. |
5066 |
Cannot delete e-mail. |
4959 |
Adding or removing e-mail recipients breaks the selection window. |
4876 |
The author of an e-mail is replaced with the project leader. |
5376 |
Server crash may occur when sending e-mails. |
5074 |
E-mail - Save option missing on imported e-mail. |
4968 |
iCalendar integration - tasks/ToDos are displayed as meetings instead of all day events depending on the e-mail system. |
5301 |
Style issue in Headers with Internet Explorer 11. |
5063 |
E-mail option is missing from the Create menu in the documents, |
Expense Report
Ref. # |
Title |
5399 |
Users do not see their expenses reports in the 'My expenses...' views. |
Genius Live
Ref. # |
Title |
4982 |
Scrollbar has disappeared in Genius Live. |
5347 |
Only the first 10 items are displayed in Genius Live. |
5296 |
Rich text formatting is not preserved in Genius Live posts. |
Genius Planner
Ref. |
Title |
5049 |
Errors can occur in Genius Planner when checking the 'Deliverable' checkbox in the properties. |
5023 |
Step names starting with a large number and containing “.” characters prevent the plan from synchronizing. |
5159 |
The load units should not be hardcoded in 'days' in the Activity properties window of Genius Planner. |
5268 |
Changing the project start date on linked activities move them to the wrong dates. |
5390 |
Server crash may occur when synchronizing a plan. |
4870 |
Recently created Sub-projects cannot be selected in the Gantt. |
5316 |
Sub-projects are being added as [Global] in the Gantt. |
5005 |
Genius Planner becomes unresponsive after inserting a resource categorized under '- Others -'. |
5042 |
Single quote characters in task types prevent Genius Planner from loading. |
5155 |
Resources are removed from the plan when renaming them from Genius Planner. |
5133 |
Planned end date is set to year 1970 when no work baselines exist in the plan model. |
5062 |
Activities without workflow are not managed in Genius Planner. |
5160 |
The physical progress field becomes not editable when changing a deliverable into a task. |
5518 |
New task dependencies are created as external links and are impossible to remove. |
Invoicing
Ref. # |
Title |
5284 |
Invoice VAT; settlement date; edition not working as expected. |
Ref. # |
Title |
#5219 |
Impossible to select the element to open in shortcuts page. |
Other
Ref. # |
Title |
5217 |
It is possible to edit a project description in an Archive database. |
4963 |
Request from trash does not work |
5217 |
It is possible to edit a project description in an Archive database. |
5167 |
Trim spaces in External links when copy/paste an URL. |
5156 |
Calendar project filter does not always apply properly. |
4134 |
Using the backspace breaks auto completion in most of the fields. |
5226 |
Login screen appearing in rich texts. |
Plan
Ref. |
Title |
5409 |
Error 'GETCOSTACTIVITY line 52' in the system events. |
5233 |
The planned rate is used instead of the actual rate when adding workload from the assignment. |
Portfolio
Ref. # |
Title |
5313 |
OBS access does not correspond to the specified security. |
5248 |
Multi-projects Gantt: missing selection fields in the 'By criteria' tab. |
5179 |
License not correctly managed in the Portfolio. |
5202 |
Critical success factors dropdown menu blanking out in Projects and Project requests. |
5189 |
JavaScript error when trying to refresh the list of projects in the Portfolio. |
5368 |
Impossible to create a multi-project Gantt based on the project status. |
5369 |
Error on working days when saving the Portfolio setup. |
5308 |
No titles in multi-projects Gantt form and impossible to delete them from the configurable view. |
5329 |
The remaining workload in the project description of the Portfolio shows the remaining cost instead. |
5366 |
Access to projects in an OBS as specified in the OBS setup does not work. |
5071 |
Impossible to open portfolios views and charts. |
5341 |
Code appearing instead of the project names when creating a multi-project Gantt from a selection of projects. |
5206 |
Add the possibility to input customers not defined in the Resources database in the project request. |
Project Request
Ref. # |
Title |
5163 |
The [Create > Budget] menu is sometimes missing from the project request. |
5154 |
Wrong data in the Costs section of the project overview. |
4801 |
Attachments are lost when promoting a project request into a project. |
5198 |
Project categories created from Setup & Keywords document are not visible in the Project requests - Configurable view. |
Project Wizard
Ref. # |
Title |
5224 |
Project Risk factor default value is 51 where it should be 50. |
5342 |
The default value for project ranking as set in the setup on a list is always overwritten with the first list value. |
5395 |
Wizard: System events generated when creating a project. |
5352 |
Project ranqking fields are always mandatory in the Wizard even if they are not mandatory in the setup |
Projects
Ref. # |
Title |
5174 |
Wrong duration in the project. |
5421 |
My projects calendar: missing filter options. |
4865 |
Import of a project template shows error because no template was selected. |
5165 |
Wrong handling of customer rates. |
4878 |
‘Error loading grid' message in the Assignments tab of a task where there are duplicated assignments. |
5199 |
Resource names in the Project list view should be without the '/CompanyName' extension. |
5323 |
Project Overviews – Configurable view Progress is always 0. |
5411 |
Actual end date is lost on a great number of projects after upgrade to new version. |
5282 |
Generic resources not replaced in assignments after request promotion with template. |
5279 |
The plan does not synchronize (was due to billing milestone without a billing date). |
5416 |
The action to put a completed assignment back to 'In progress' status does not appear. |
5241 |
Make sure that automatic processing of the documents will not break the rich text fields. |
5044 |
Project filter by criteria: when only one choice is available, it is split. |
5386 |
Company names containing a comma are split in the Customer field. |
5428 |
Task deltas in embedded view do not make sense. |
5320 |
A hyphen is displayed after the company name in the views if no location was specified for the company. |
5252 |
Actual work of 0 automatically set to planned in completed assignments. |
5270 |
Missing budget period in Tasks. |
4890 |
Replacing generic resources can lead to conflicting assignments. |
5047 |
When renamed in the Setup & Keywords document, project categories are not updated when a project is opened in read only mode. |
4895 |
Migration agent: error on project overviews from older versions. |
4485 |
The 'Progress' field in the project description never displays the physical progress. |
5210 |
Project planned start date column shows the wrong date. |
Resources
Ref. # |
Title |
5481 |
My unavailability calendar view not refreshing on Internet Explorer. |
5041 |
Error on Resource document when there are too many resources. |
4922 |
Calendar view is not working properly in Internet Explorer 10. |
5191 |
It is not possible to input the currency in a rate. |
4355 |
New unavailability: add the possibility to select PM/AM over multiple days. |
5058 |
Impossible to bookmark any view from the Resources database. |
5256 |
Unavailability: End date should align itself with start date when it is modified. |
5413 |
Error 'Null pointer exception' when displaying a resource Gantt. |
5462 |
Newly created resources cannot log in. |
5311 |
‘Error loading data' while creating Resource rates. |
5412 |
This is not possible to replace generic resources having the extension '/CompanyName'. |
5121 |
Users cannot login anymore after the password was changed. |
5402 |
User part in license information screen is not readable. |
5400 |
Impossible to select the destination databases when publishing the selected resources. |
4728 |
Rename resource bulk action dialog: no resource can be selected after choosing projects. |
5278 |
Renaming a resource from the Resource document takes a long time and remains idle. |
5056 |
Internet Explorer causes problems with Soft Booking. |
5109 |
Cannot import resources from NABs that are located in a subdirectory path on the server. |
4736 |
Impossible to delete a Company document and no message pops up. |
5300 |
Resources rates setup interface issue, nothing is checked in the management type. |
5128 |
Company name lost when renaming a material resources with the same name. |
5209 |
A user without a license can create an Unavailability document. |
Risk
Ref. # |
Title |
5215 |
Risk categories that contain an apostrophe are broken in the Risk form |
5334 |
Mitigation plan in the Risk configurable view is empty. |
Setup
Ref. # |
Title |
5131 |
Empty grouping in the setup of the Participants tab breaks the project wizard. |
4908 |
Impossible to enter new 0% rates in the General setup of Timesheets database. |
5101 |
Error 'Name is a required field' when saving a navigation context or navigation tabs. |
5387 |
Changing a profile in the Portfolio does not update the resources. |
5064 |
Risks classification tree labels are not properly updated in child documents. |
5251 |
Agent execution error 'Send reminders for unfilled timesheets' is displayed when running the agent: from the interface. |
Timesheets
Ref. # |
Title |
5246 |
View 'Time details - To be approved - Personal (week)' is not grouped by week. |
5148 |
It is possible to add time in locked timesheets with the stopwatch. |
5194 |
The agent to update the project names in timesheets does not process all the details. |
5277 |
Not possible to input the denial reason when denying timesheets or expense reports from the document. |
5118 |
The denial comment is not visible in the timesheet form. |
5302 |
Save & Notify menu on three lines in Internet Explorer 11. |
5437 |
Error when trying to add task to timesheet. |
5008 |
Error 'Type mismatch 49' when using the stopwatch to input time. |
5439 |
German numbers not properly handled in timesheets. |
5403 |
Some timesheet details are not billable when their type is empty. |
5060 |
Some timesheets have a total of 0 after migration. |
5283 |
The status of the timesheet details is not updated when approving a timesheet from Genius Live. |
5048 |
The totals of a new empty timesheet are empty instead of 0. |
5457 |
Internet Explorer 11: the Java applet is launched when opening a Timesheet. |
5384 |
The date range specified in the setup is not considered in Timesheets. |
5265 |
Impossible to save the Timesheet archiving setup. |
5359 |
Time reporting - Some timesheet details were not generated. |
5054 |
Send reminder for unfilled timesheets includes excluded users in the summary e-mail. |
5162 |
Some reminders for incomplete timesheets are not sent. |
5307 |
Input time dialog box shows numbers with too many decimals. |
5105 |
Cannot create calculated timesheet and set it 'By default'. |
5203 |
Remaining work requests approved value is in the wrong unit. |
5406 |
Denying already approved timesheet does not work when approval is set on détails |
Tollgate
Ref. |
Title |
5245 |
Unable to use success factors in a project template. |
5378 |
Special characters are not displayed correctly in the Phase-Tollgate chart. |
Views Legacy
Ref. |
Title |
5257 |
Bookmarking legacy mono views (My …) is not working. |
Workflow
Ref. |
Title |
5232 |
Project leader receives notifications for budget lines being assigned to a resource who is not a member of the project. |
5175 |
A comma in status remarks splits the remark. |
Comments